Exploring Development and Engineering

A case-study via drinking water

Milind Sohoni CTARA, CSE, IIT-Bombay

(2)

Introduction

Academic journey:

B.Tech (CSE) 1982-86 (H4), andPh.D. in 1992 (H1).

M.S. from University of Illinois, Urbana-Champaignin 1989.

Faculty in CSE since 1994.

Experience (before 2005):

visiting faculty at University of Chicago for many years.

consulted with many companies including Ericsson Research, Honda Research, worked with Western Railways

Conundrum

Theprocesses and systems in foreign lands. Why are we like this?

I corruption? colonization? poverty? caste system? Whats IIT go to do with this?

(3)

Introduction

Academic journey:

B.Tech (CSE) 1982-86 (H4), andPh.D. in 1992 (H1).

M.S. from University of Illinois, Urbana-Champaignin 1989.

Faculty in CSE since 1994.

Experience (before 2005):

visiting faculty at University of Chicago for many years.

consulted with many companies including Ericsson Research, Honda Research, worked with Western Railways

Conundrum

Theprocesses and systems in foreign lands.

Why are we like this?

I corruption? colonization? poverty? caste system?

Whats IIT go to do with this?

(4)

2005-The Gudwanwadi Project

Objective : to investigate the interface between technology and developmentand the role of IIT in it.

Methodology concrete development problem and direct participation.

A teaching and research initiative

380 Thakar people.

200 animals.

40 households.

And an acute shortage of water for 5 months.

Technology Choice

Build a check-dam.

(5)

Multi-agency

Faculty, students of IIT, ADS (a local NGO), Gangotree-an implementer.

(6)

People

Intensive village level work.

(7)

Machines

(8)

Our Students

(9)

Our then Director

(10)

On July 1st, 2006-Full

85m long, 20,000 cu.m. storage, 25 lakhs cost. Money raised through alumni (esp. a huge chunk from Shridhar Shukla).

(11)

Success...mixed

Water in check-dam till aboutJan 15-30.

Running water (for washing etc.) till about Feb 20th.

Drinking water in borewells till about March 15.

Acuteness of problem reduced by 2-3 months

Hard research

Hydrogeological surveys and testing

Protocols for

construction-2008-grouting Simulation

cost-effectiveness-Rs 200 per cu.m.

(12)

Key learning

Huge number of engineering problems amenable to academic research.

Poor understanding of socio-economic and governance issues.

Poor institutional infrastructure at all levels for knowledge generation and transmission.

On the whole..

A lot of things that IIT must learn to do.

research for delivery in concrete situations development of field level teaching

inter-disciplinary research-end-use defined departments!

all things the modern western university has been doing for long!

(13)

Wider Perspective: Jal-Swarajya

Move villages to community owned drinking water systems.

(14)

A Study: Thane District

2000 villages in Maharashtra alone in Phase I

Water sources

I lifting from existing reservoirs and

I ground-water

Poor performance of ground-water based solutions.

Poor quality groundwater testing and data.

Capacity building is essential.

(15)

The Karjat Project

Disha Kendra: A popular NGO in Karjat-Khalapur area, led by Nancy Gaikwad.

January 2010: approached CTARA with problem of widespread drinking water collapse in North Karjat taluka.

Their strategy : RTI and dharnasat taluka office.

(16)

Our Plan

Question 1: Is there adequate groundwater at all?

I GSDA, our own tests. (Sanjiv, Vishal)

Question 2: Are there administrative problems?

I lack of information, improper yield tests, etc.

Question 3: What is to be done?

I Groundwater recharge structures?

I Surface water supply? (Abhishek, Vikram and Janhvi)

(17)

The Karjat Pipeline feasibility study

Study Objective

Is it possible to have a wide-area rural pipeline scheme for the area?-a basic techno-economic feasibility study.

use MJP normsexactly as far a possible.

See if capital costs and energy costs fit within norms.

Abhishek Sinha, Vikram Vijay: two dual-degree Civil. Engg.

students,Janhvi Doshi, 4th year B.S., summer intern from Rice University.

3 months of field work: May-July 2010. Report-writing 1-2 months.

Rs. 1 lakh budget.

(18)

Hamlets and clusters

(19)

Overall map

Lots of nice optimization problems, use of simulators, GIS and so on.

(20)

Key Findings

1

200 LPCD 40 LPCD

Daily Demand 19.47 MLD 3.90 MLD

Net Investment Rs. 57.21 crores Rs. 17.19 crores Cost per person Rs. 7051 Rs. 2119

Energy costs of Rs. 4.51 per cubic meter, at Rs. 5 per unit and 75% pump efficiency.

I This may reduce further from better choice of lift-up point, agreement between MJP, Irrigation and Tata Power.

O&M costs and establisment costs to be added.

Pipeline water supply for North Karjat (pop. 51,000 in 70 hamlets) is techno-economically feasible

.

1www.cse.iitb.ac.in/∼sohoni/karjatfinal.doc

(21)

Post-report

Report submitted to Disha Kendra for dissemination.

I Keyknowledge input to serve as rallying point.

Report submitted to Karjat MLA, Shri. Suresh Lad.

And to MJP office and Minor Irrigation office in Karjat.

Towards implemention:

Report adopted by GPs.

Formal expression of demand (scarcity) submitted to ZP and MJP.

New Research

Single vs. Multi village schemes and institutional issues IIT as consultant to rural bodies

(22)

Groundwater

Basic question: Groundwater sufficiency and distribution.

conflicting narratives of taluka administration and inhabitants

I Karjat again...

very poor quality and sparse groundwater data.

I 9 observation wells for the whole taluka

(23)

The GP Water Document

To maintain reliable data and assess need.

To prepare a framework for policy implementation.

(24)

Seasonality and well yields

Need:to assess supply and to predict

Example: column=7m, WT=-4implies

recharge 7 cu.m. /day.

Generated in initial years

Reliable and Accurate

A more refined

understanding of supply and demand.

water column

recharge Well Recharge Curves

−2mmonsoon

−4mwinter

−6mspring

−8msummer

(25)

Simulator Project- since 2008

Role in watershed development.

Planning of small structures for drinking water.

But how did I get here from Gudwanwadi?? Yeh kahan ...

(26)

Simulator Project- since 2008

Role in watershed development.

Planning of small structures for drinking water.

But how did I get here from Gudwanwadi?? Yeh kahan ...

(27)

Conclusion- a new paradigm at CTARA

The bottom 80% : beneath the market and the state-an ideal laboratory!

Core issues: food, water, energy, livelihoods, public health- simple principles and great returns!

Delivery: designs, implementations, studies to a concrete beneficiary-the creation of knowledge! .

For good engineering-with development as a side-effect.

Nothing new-HBS : ” start with the proximate customer” or Sam Pitroda: ” engg. as if the common indian mattered. . .”

A New Contract: Engagement

Anjap-Sugwe drinking water scheme • Malvan taluka transport plan

•Second crops in Dimbhe • Waste management in Guhagar

(28)

Conclusion- a new paradigm at CTARA

The bottom 80% : beneath the market and the state-an ideal laboratory!

Core issues: food, water, energy, livelihoods, public health- simple principles and great returns!

Delivery: designs, implementations, studies to a concrete beneficiary-the creation of knowledge! .

For good engineering-with development as a side-effect.

Nothing new-HBS : ” start with the proximate customer” or Sam Pitroda: ” engg. as if the common indian mattered. . .”

A New Contract: Engagement

Anjap-Sugwe drinking water scheme •Malvan taluka transport plan

•Second crops in Dimbhe • Waste management in Guhagar

(29)

Thanks

References

Related documents

 Use of multiple sources: Advocates for use of surface water in case of high development of ground water, reliance on multiple water sources..  Management Information System

It contains the following data fields: name of the block, name of the gram panchayat, name of the habitat, total population, number of households, individual Public Water System

January 2010: approached CTARA with problem of widespread drinking water collapse in North Karjat taluka.. Ashok Jangle (DK): various RTIs and collation of

North Mokhada rural regional scheme: Feasibility Study, 2012. The Problem: Widespread drinking water stress,

I District resource maps, better models for ground water District Planning tools. I get CEO/collector

Piped water supply, rural water supply, piped network design, drinking water, domestic water, Karjat, Maharastra...

Measuring the Impact of West Bengal Drinking Water Sector Improvement Project: A Baseline Study Figure 1: Theory of Change—West Bengal Drinking Water Sector Improvement Project

Progress on access to drinking water (target 6.1) has a promoting influence in the areas of food, nutrition and agriculture; education; and economic development. Clean drinking water