• No results found

Each Micropile is Loaded Directly

N/A
N/A
Protected

Academic year: 2022

Share "Each Micropile is Loaded Directly"

Copied!
20
0
0

Loading.... (view fulltext now)

Full text

(1)

Micropiles – Design and its Applications

1

INTRODUCTION

 A micropile is a small-diameter (typically less than 300 mm), drilled and grouted replacement pile that is typically(up to 20% As/Ac)reinforced.

 A micropile is constructed by drilling a borehole, placing reinforcement, and grouting the hole.

 Micropiles can withstand axial and/or lateral loads.

(2)

Micropile Classification System

Ref: FHWA-NHI-05-039, AASHTO LRFD 4th Edition, Interim 2008

3

Case 2 90% of International Applications

~ 100% of North American Applications Case 1

Very Few Applications in the USA

•Based on Design Application

•Based on Grouting method

•Based on Design Application

Case 1 Micropiles

4

Each Micropile is Loaded Directly

Primary Resistance is Provided by Steel

Reinforcement and Side Resistance over Bond Zone

Each Micropile Designed to Act Individually, Even When in Groups

AASHTO – Minimum spacing of 30 inches or 3 pile diameters, whichever is greater

Must check for group affects due to axial compression/tension or lateral loads

(3)

Case 1 Micropiles (After FHWA NHI-05-039) 5

Network of Micropiles

Act As Group to Reinforce The Soil Mass

Each Micropile is Lightly Reinforced

Design Procedures Not Fully Developed

Case 2 Micropiles

(4)

Case 2 Micropiles (After FHWA NHI-05-039) 7

Micropile Installation (After: FHWANHI-05-039) 8

(5)

Based on Grouting method

 The method of grouting is generally the most sensitive construction control over grout/ground bond capacity . Grout-to-grout capacity varies with the grouting method.

1) Type A: Gravity Grout

2)Type B: Pressure through Casing 3)Type C: Single Global Post Grout

4)Type D: Multiple Repeatable Post Grout

Type A: Here the grout is placed under gravity head only using sand-cement motors or neat cement .

TypeB:

1) In this type neat cement grout is placed into the hole as the temporary steel casing iswith drawn.

2) Injection pressures varies from 0.5to 1.0 MPa.

The pressure is limited to avoid fracturing of the surrounding ground.

(6)

Type C:This is done in two step process:

1) As of Type A

2) Prior to hardening of the primary grout, similar groutis injected one time via a sleeve grout pipe at pressure of at least 1.0MPa.

Type D: This is done in two step process of grouting similar to Type C with modifications to step 2 where the pressure is injected at a pressure of 2.0 to 8.0MPa:

Figure 5: Based on method of grouting

(7)

CONSTRUCTION SEQUENCES

Installation process in accordance with the requirements of NBN EN1536:1999

1) Positioning and drilling of the first section of the drill casing (recoverable steel casing as temporary support during the boring process).

2) While drilling, the drill casing – inside equipped with a drilling head fixed on a rod - is oscillated into the soil.

(back and forth movement / twisting in place).

3.As the drilling process progresses, soil is removed from the borehole by the excavating and additional sections of casing are jointed (added) to protect the soil from collapsing into the borehole during drilling..

5.After reaching the design depth, clean-up of the borehole front, removal drilling tool, drilling fluid (water) pumped out from the bore Formation of the pile : insertion and lowering of the reinforcement cage, pouring of the concrete

6. During the continuous concreting process, the temporary casing elements are progressively withdrawn whereby the concrete forms the pile shaft.

(8)

Figure 7: Micropile construction squences using

Basic Design Process

16

Step 1 >>>Prepare preliminary design

Step 2 >>>Evaluate geotechnical capacity

Step 3 >>> Load Testing

(9)

Step 1>>> Prepare Preliminary Design

17

Select Micropile Spacing

Min 30 inches or 3 diameters, whichever is greater

Based on situation (e.g., existing footing, clearances, etc)

Select Micropile Length

Consider compression, uplift, lateral loads, scour, downdrag, group affects

Max length using common track-drilling equipment is > 300 feet but most are on order of 100 feet

Select Micropile Cross Section

Allow use of common casing sizes for material availability;

Use casing vs rebar reinforcement >>better lateral and axial capacity

Step 2 >>Evaluate Geotechnical Capacity

Establish Stratum for Bond Zone

Certain soils not generally suitable (e.g., organics, cohesive soils having LL>50, PI>20); (if must be used, include comprehensive testing, increased FS)

Select Ultimate Bond Strength

PG-Allowable = PUltimate/FS

RR = φ Rn = φqp Rp + φqs Rs = φqp (qp Ap) + φqs ds άb Lb)

Consider end bearing in high quality rock only with adequate verification of rock quality and construction methods to obtain good contact;

(10)

Contd…

19

 Evaluate Micropile Group Compression Capacity

Cohesive or Cohesionless Soils (Block & Punching Failures)

 Evaluate Micropile Group Uplift Capacity

Cohesive or Cohesionless Soils (Block Failures)

Evaluate Micropile Group Lateral Capacity

Refer to procedures for driven piles and drilled shafts

(FHWA-NHI-05-42 and FHWA-IF-99-025;AASHTO LRFD Int 2008,Section 10.7)

Evaluate structural capacity of pile(s)

Evaluate Soil-Structure Interaction (e.g. LPILE)

Consider Battered Piles, Buckling and/or Seismic Effects

Step 3 >>Load Testing

Compression Load Test ,

Tension Load Test ;

Lateral Load Test;

20

(11)

Compression Load Test

21

Tension Load Test

(12)

23

Lateral Load Test

Drilling Techniques

24

Single Tube Advancement

Rotary Duplex

Hollow Stem Auger Casing

Drill Rod Ground Surface

Drill Bit

Casing Rotary Drill Bit

Drilling Fluid

Rotary Duplex

(13)

Drilling Machines

25

Rotary Eccentric Percussive Duplex Duplex Casing and Roller Bit

Composite Reinforced Micropile

Lp

Lb

db

(14)

Possible Applications of Micropiles

As Alternate Deep Foundation Type, Especially Where Piles Penetrate Rock;

Where Spread Footings Are Feasible but There Is Potential For Erosion or Scour

Support System Close to Existing Structure;

Risk of Liquefaction From Pile Driving;

27

Ref: FHWA NHI-05-39, Table 3-1

Slope Stabilization And Earth Retention [Case 1 and Case 2]

Ground Strengthening [Case 1 and Case 2]

Settlement Reduction

[Case 2]

Structural Stability

[Case 2]

In-Situ Reinforcement [Case 1 and Case 2 Micropiles]

Earth Retaining Structure Foundations

Foundations For New Structures

Underpinning Existing Foundations

Seismic Retrofitting

Scour Protection

Repair/Replace Existing Foundations

Stop/Prevent Movement

Upgrade Foundation

Capacity Structural Support

[Case 1 Micropiles]

(Est 0-5% of world applications)

(Est 95% of world applications)

Overview of Micropile Applications

28

(15)

Limitations for Micropiles

29

Vertical micropiles may be limited in lateral capacity;

Cost effectiveness;

Potential buckling under seismic loading and liquefaction

But need to consider methods available to quantify and/or deal with these limitations

Micropile Installation

Williamsburg Bridge , New York Seismic Retrofit,Los Angeles, California

(16)

Design and Construction of Micropiles

by S.S. Liew and C.C. Fong

Gue & Partners Sdn Bhd, Kaula Lampur, Malaysia

(29-30 Sept,2003)

Abstract: “This paper discusses the micropile classification, design concept, problem associated with the common installation methods, construction control and performance of this pilling system”

31

Overview of Research work on Micropiles

32

(17)

33

(18)

35

36

(19)

37

CONCLUSIONS

Micropiles can be used as a normal foundation piles and compensation piles for remedial works, especially with areas with site constraints. It can be costly option to support lateral loads and huge bending moments.

Acknowledgement

With sincere thanks to

(20)

39

REFERENCES

Bruce, D. A. (1988),“Developments in Geotechnical Construction Processes for Urban Engineering”,Civil Engineering Practice, Vol. 3, No. 1, Spring, pp. 49-97.

Weltman, A.(1981).A review of micropiles types. Ground engineering, May, 43-47

FHWA (1997),“Drilled and Grouted Micropiles, State-of-Practice Review”, Bruce, D. A.

and Juran, I., Reports No. FHWA-RD-96-016, 017, 018, and 019.

AASHTO LRFD Bridge Design Specifications 4thEdition, 2007, Interim 2008, Section 10.9;

FHWA (2000), “Micropile Design and Construction Guidelines Implementation Manual”,Armour, T., Groneck, P., Keeley, J., and Sharma, S., Report No. FHWA-SA-97- 070.

References

Related documents

This report provides some important advances in our understanding of how the concept of planetary boundaries can be operationalised in Europe by (1) demonstrating how European

It is made up of steel pipes called drill pipes, drill collars (below the drill pipes are thicker – walled, heavier, stronger pipes to put weight on the bottom of the drills string

The Congo has ratified CITES and other international conventions relevant to shark conservation and management, notably the Convention on the Conservation of Migratory

INDEPENDENT MONITORING BOARD | RECOMMENDED ACTION.. Rationale: Repeatedly, in field surveys, from front-line polio workers, and in meeting after meeting, it has become clear that

The semi globular species of inhibitor products may be attributed to the molecular association of the inhibitor molecules in the acid solution, resulting in the

The scan line algorithm which is based on the platform of calculating the coordinate of the line in the image and then finding the non background pixels in those lines and

Drilling process is highly depended on the cutting parameters (i.e. Feed, Speed, and Drill Diameter), tool geometry, instrument and workpiece material, delamination along with

The present study focused on the effects of drilling parameters such as drill speed, feed rate and thickness of the composite plates; each varied in four different levels,