PRILIMINARY DESIGN REPORT
Safe drinking water is primary need of life. Contaminated drinking water is causing health hazards to millions of people. Scarcity of water is also one of the problem which hampers the social and economical development of the people.
Provision of safe drinking water deserves priority to improve the health and economical development of the area . Govt. of Telangana has announced a prestigious project “Telangana drinking water grid” in which the aim is to provide safe drinking water to all the habitations from surface sources on sustainable basis with enhanced supply level of 100 liters per head.
Khammam is one of the 10 districts in Telangana state. Due to state bifurcation 5 mandals in full and 2 mandals partially were merged in to AP state. The present population of the district is 26.83 Lakhs. There are 19663 hand pumps functioning in the district.and 23 CPWS schemes, 1335 PWS schemes, 264 MPWS schemes and 718 Direct Pumping schemes functioning in the total district. Present rate of supply is 40 LPCD. For all the schemes other than CPWS schemes, sources are either bore wells or open wells which are dependent on ground water. Due to frequent failure of monsoons in the district, ground water is depleting as a result many habitations which are partially covered earlier are again looking for relief as the source infrastructure provided is in need of either augmentation or replacement.
Hence there is need for creation of sustainable sources on long term basis.
Detailed preliminary design report is here with prepared for preparation drinking water Grids in Khammam district keeping in view the available surface water sources, and also the requirement as per population in district.
For formation of drinking water grid in district available major sources are identified. Following are the major sources existing in the district.
1) Godavari river.
2) Kinnerasani reservoir fed by Kinnerasani river.
3) Palair reservoir fed by NSP canal.
4) Wyra reservoir fed by NSP canal.
Three grids are formulated in the district 1 in Godavari basin and 2 other grids in Krishna basin covering entire 41 Mandals in the district.
Grids in the District
Available major Sources are identified in the district and accordingly three Grids are formulated in the District covering 41mandals as follows.
Grid Name No. of Mandals Grid Source Covering
Grid 25 07 Palair reservoir.
Grid 24 22 Godawari & Kinnerasani Reservoir.
Grid 26 11 Wyra reservoir.
WATER REQUIRMENT:
Total population of the district is 26.83Lakhs with 19.72Lakhs as rural population and 7.10 Lakhs as urban population. 6.874 TMC water is required for drinking water needs in the district by 2048 with design period of 30 years. At present present 1.191TMC is being tapped from these sources for present functioning schemes for both rural and urban and balance requirement of 5.683 TMC is to be drawn through the Grid is as follows source wise .
Sl.
No Source
Proposed demand on source
Present existing drawl
Balance demand to be drawn through grid
1 Godavari river at Pusur 0.114 0 0.114
2 Godavari river at Parnasala 0.180 0 0.180
3 Godavari river anicut @
Dummugudem 2.988 0.232 2.756
4 Godavari at Bhadrachalam. 0.210 0.058 0.152 4 Kinnarasani river at Gundala 0.056 0 0.056
6 Palair reservoir 2.135 0.763 1.372
7 Wyra reservoir 1.191 0.137 1.053
Total:: 6.874 1.191 5.683
DESIGN CRITERIA ADOPTED:
The design Parameters adopted for this Project components are detailed below
1.Design Period:
The year 2018 is taken as the proposed year of commissioning and considered as base year.The ultimate design period of the project is considered as 30 years over the base year.2033 is considered as prospective year with 15 years prospective period.
2.Design Population:
The base year population is worked out by adding population increase at 0.80 % growth rate for Rural and 2.00 % growth rate for Urban from 2011 to 2018.The ultimate design population is worked out by increasing 0.80 % for Rural & 2.00 % for Urban in geometric progression for 30 years over the base year population.
3.Design Parameters:
Established parameters are followed in the system design.
Sources and Transmission Pipelines are designed for ultimate demand.
Sumps ,Balancing reservoirs and pumping machinery are designed for prospective Population.
4.Service level:
Supply level of 100 lpcd at consumer end is considered with 100 lpcd production at Treatment Plants and with 105 lpcd at drawl at Raw water Intakes.
5.System Design Criteria:
Operation period of pumping machinery : 22 Hours
Clear water sumps : 150 minutes
Service Storage Reservoirs : Capacity with 50 %
prospective daily Demand
Balancing Resrvoirs : 30 minutes
Pumping Machinery : with 15 yrs design period : Preliminary Design
as per discharge and Head, Detailed design as
per system Curves
Distribution system : 6 Hours supply GRID WISE DETAILS
GRID 25 (Palair Grid):
In this Palair Grid, Palair reservoir is taken as Source. Palair reservoir is situated at Kusumanchi mandal and it is having feeding from NSP canal.
Storage capacity of this reservoir is 2.52 TMC. (7) mandals of Khammam Dist. And 17 Mandals , 2 Muncipalities of Warangal dist.are proposed for coverage with this source with population coverage of 4.16 Lakhs of Khammam dist. And 10.22 Lakhs of Warangal dist. total Water requirement for this Grid 3.609 TMC for 2018 projected population.
1) Chintakani
2) Khammam-Urban 3) Khammam-Rural 4) Kusumanchi 5) Mudigonda 6) Nelakondapally 7) Tirumalaipalem
For Warangal district in this Estimate it is proposed only Intake well, Power supply, and Raw water pumpsets, and the remaining items are proposed by SE,RWS&S, Warangal separately.
a) For Kusumanchi mandal there are existing 2 nos. 8 MLD RSF’s One at Palair village and other at Gurvaigudem village. From Palair Head works safe drinking water is supplying to Entire Tirumalayapalem mandal and part of Kusumanchi mandal. From Gurvaigudem Head works Drinking water is supplying to Part of Kusumanchi mandal and proposed to supply entire Nelakondapally mandal@ 40 LPCD.
As per Grid norms to 100 LPCD the two existing head works are sufficient for only Kusumanchi mandal, and separate head works are proposed for Tirumalayapalem and Nelakondapally Mandals.
b) For Tirumalayapalem Mandal it is proposed to draw clear water from Proposed 30.00 MLD WTP near gurvaigudem village by pumping up to Bandampally village and proposed 600 KL clear water sump ,90 KL OHBR at Zinkalagudem , 60 KL OHBR at Bachodu by utilizing the existing OHBR,s at Bandampally, Dammaigudem, and Bachodu Thanda. The xisting Secondary mains utilizing upto 100 lpcd level and from there parallel gravity mains are proposed
c) For Nelakondapally Mandal it is proposed to draw Clear water from Proposed 30.00 MLD WTP at Gurvaigudem village by Gravity for both Nelakondapally and part of Mudigonda mandals through Proposed 200 KL OHBR at Gurvaigudem village. The Existing Secondary mains utilizing upto 100 lpcd level and from there parallel gravity mains are proposed
d) For Mudigonda mandal there is Ongoing CPWS Scheme by taking source in Palle Cheruvu of Mutharam village which having NS canal feeding and using as SS tank for canal closure period, to serve 33 habitations of Mudigonda mandal @ 70 LPCD. There is Ongoing 8.00 MLD RSF,850 KL Clear water Sump,120 KL OHBR with 30 mts staging at head works to serve 23 habitatios and 60 KL OHBR with 30 Mts. Staging at Mudigonda to serve 10 Habitations and gravity mains . To achieve as per grid norms the existing head works is restricted to 23 habitations which are at down side.
It is proposed to supply clear water to 10 habitations from Proposed 200 KL OHBR at Gurvaigudem through Gravity which is proposed Centralised head works near Gurvaigudem village of Kusumanchi mandal.
e) For Khammam ( R ) mandal there is Ongoing CPWS Scheme by taking source in Edulla Cheruvu of Edulapuram village which having NS canal feeding and using as SS tank for canal closure period, to serve 68 habitations of Khammam ( R ) mandal @ 40 LPCD. There is Ongoing 6.50 MLD RSF,900 KL Clear water sump,200 KL OHBR with 30 mts staging at head works and gravity mains .
To Achieve Grid norms balance head works of 10 MLD proposed at Edulapuram. It is proposed to take raw water directly from Palair reservoir through canal system to existing MI tank which is proposed to deepen for summer period. It is proposed 10.00 MLD RSF at Head works ,600 KL Clear
water sump at Head works ,250 Kl OHBR at
Arempula village and Gravity mains.
f) For Khammam ( U ) mandal there is Ongoing CPWS Scheme by taking source in Velugumatla Cheruvu of Puttakota village which having NS canal feeding and using as SS tank for canal closure period, to serve 60 habitations of Khammam ( U ) mandal @ 40 LPCD. There are Ongoing 5.00 MLD RSF,500 KL Clear water sump at head works near Puttakota ,90 KL GLBR at Hillock and gravity mains .
To Achieve Grid norms new head works proposed for balance capacity, it is proposed to take raw water directly from Palair reservoir through canal system to existing MI tank which is proposed to deepen for summer period. It is proposed 5.00 MLD RSF at Head works ,500 KL Clear water sump’s 2 Nos. One at Hear works and other at Zinkala Thanda,100 Kl GLBR at Zinkala thanda Hillock and Gravity mains.
g) For Chintakani mandal there is Existing CPWS Scheme by taking source in Nalla Cheruvu of Chintakani village which having NS canal feeding and using as SS tank for canal closure period, to serve 25 habitations of Chintakani mandal @ 45 LPCD. There are Existing 5.00 MLD RSF,400 KL Clear water sump at head works near Chintakani , 2 nos. 60 KL OHBR with 30 mts. One at chintakani to serve 13 Habitatios and other at Raghavapuram to serve 12 habitations and gravity mains to 13 habitations.
To Achieve grid norms the existing Head works is restricted to 13 habitations, and existing OHBR at chitnakani is proposed to serve 6 Habitations , existing OHBR near Raghavapuram is proposed to serve 10 habitations. New head works proposed for balance 12 habitations, it is proposed to take raw water directly from Palair reservoir through canal system to existing MI tank which is proposed to deepen for summer period.
It is proposed 5.00 MLD RSF at Head works ,500 KL Clear water sump,40 Kl OHBR with 30 mts. Staging at Nerada village to serve 4 Habitations ,60 Kl OHBR with 30 mts.staging at Patharlapadu village to serve 5 habitations and Gravity mains.
In accordance to the above the Governmant of Telanganahas accorded Administrative sanction for c/o Intake wells, WTP, Sumps, R aw water pumping mains in Phase – I an amount of Rs. 16000.00 Lakhs vide GO.Rt. No.82 , Dt,07-02-2015 of PR& RD.
Accordingly the detailed Estimate is prepared with the following provisions in this Estimate.
1) C/O 46.5X 12 mts. Rectangular Intake well for 17 Mandals of warnagal Dist, and 3 Mandals of Khammam dist.
2) C/O Raw water inflow channel in the bed of Palair Reservoir 3) Formation of Ring bund around the proposed Intake well 4) Formation of Approach road cum bund to Intake well
5) C/O Raw water pumping main from Intake well at Palair Reservoir to 30 MLD WTP at Gurvaigudem village
6) C/O 30.00 MLD Rapid sand Filters near Gurvaigudem village
7) C/O 2 nos. of 1100 Kl clear water sumps at Gurvaigudem head works 8) C/O 24x6 Mts. Pump house at Gurvaigudem Head works
9) C/O Compound wall to GurvaigudemHead works
10) Fixing of 900 HP VT Motor 6 Nos. 2 being stand by for Warangal Dist.
11) Fixing of 200 HP VT motors 3 Nos. 1 is being stand by for WTP at Gurvaigudem
12) Supply and fixing of 80 HP HSC motors 3 nos one is being stand by for Tituemalayapalem mandal at Gurvaigudem head works
13) Supply and fixing of 50 HP HSC motors 3 nos. one is being stand by for Nelakondapally Mandal OHBR at Gurvaigudem Head works
14) C/O 10 MLD Rapid sand filters near Edulapuram village for Khammam ( R ) Mandal
15) C/O of 600 KL clear water sump at Edulapuram Head works
16) C/O Summer storage tank in the bed of Edulla Cheruvu by deepening of Existing Mi tank for canal closure period.
17) C/O 10 MLD Rapid sand filters near Puttakota village for Khammam ( U ) Mandal.
18) C/O of 500 Kl clear water sump at Puttakota head works,
19) C/O Summer storage tank in the bed of Velugumatla Cheruvu by deepening theexisting Mi tank for canal closure period,
20) C/O 5.00 MLD Rapid sand filters near Chintakani village for chintakani mandal,
21) C/O 400 KL clear water sump at Chintakani village,
22) C/O Summer storage tank in the bed of Nalla cheruvu of Chintakani by deepening the existing Mi tank for canal closure period.
Provisions has been made for CED, VAT Workers welfare cess,Power supply, Other departmental permission charges and other unforeseen items.
The Detailed Estimate is prepared as per meating minutes of Chief Secretary to Government of Telangana as per SSR for current year 2014-15 and Steel, Cement rates of
Assistant Engineer Dy.Executive Engineer Executive Engineer CPWS,Khammam RWS&S,SD, Khammam RWS&S,Divn., Khammam
Superintending Engineer, RWS&S.Circle, Khammam.
ABSTRACT ESTIMATE
Telangana Drinking water Grid : Khammam Dist.
Name of the Segment : Palair Segment Number : 25
Segement : Construction of Intake well in Palair Reservoir for 17 Mandals of Warangal Dist.
And 3 Mandals of Khammam dist, WTP for 4 Mandals of Khammam dist.
Estimate amount Rs.
In Lakhs 16000.00
Sl.
No. Description of item Qty. unit (lakhs )Rate Amount (lakhs) 1 Construction of 46.50x13.45 mts. Intake well cum
Pump house 1 No 1100.00 No 1,100.00
2 Construction of VRCC lead channel from Reservoir
bed to Intake well 1 No 350.00 No 350.00
3 Formation of Approach Road to Intake well 1 No 60.00 No 60.00
4 Formation of Ring bund to Intake well 1 No 45.00 No 45.00
5 Construction of 30.00 MLD RSF at Gurvaigudem (
V ) of Kusumanchi ( M ) 1 No 1000.00 No 1,000.00
6 Construction of 1100 KL Clear water sump at
Gurvaigudem Head works 2 No 135.00 No 270.00
7 Construction of 24X6 Mts. Pump house at
Gurvaigudem Head works 1 No 25.00 No 25.00
8 Construction of Watchman Quarter at
Gurvaigudem Head works 1 No 8.75 No 8.75
9 Construction of Compound wall to Gurvaigudem
Head works 1 No 45.00 No 45.00
10 Pump sets
HP No Location
1200 6 VT pumpsets at RW collection well to Hed works at Madiripuram for Warangal dist. With 128407 lpm and 69 mts. stastic head
7200 HP 0.110 H.P 792.00
200 4 VT pumpsets at RW collection well to Hed works at Gurvaigudem for 2 mandals of Khammam dist. With 14878 lpm and 25 mts. static head
800 HP 0.150 H.P 120.00
80 4 HSC pumpsets sump at Head works to OHBR at Head works with 7329 lpm and 60.00 mts. total head
320 HP 0.150 H.P 48.00
60 4 HSC pumpsets sump at Head works to Sump at Bachode & Bandampally with 5552 lpm and 55 mts. Total head
240 HP 0.150 H.P 36.00
11 Construction of Raw water pumping main with 600 mm dia. DI K-9 S/S pipes from Intake well at Palair reservoir to Head works at Gurvaigudem
1 No 900.00 No 900.00
12 Construction of 10.00 MLD RSF at Edulapuram (
V ) of Khammam ( R ) ( M ) 1 No 450.00 No 450.00
Sl.
No. Description of item Qty. unit (lakhs )Rate Amount (lakhs) 13 Construction of 600 KL Clear water sump at
Edulapuram Head works 1 No 47.00 No 47.00
14 Construction of summer storage tank in the bed of
Edulla Cheruvu of Khammam ( R ) 1 No 1200.00 No 1,200.00
15 Construction of 5.00 MLD RSF at Chintakani ( V )
of Chintakani ( M ) 1 No 250.00 No 250.00
16 Construction of 400 KL Clear water sump at
Chintakani Head works 1 No 40.00 No 40.00
17 Construction of summer storage tank in the bed of
Nalla Cheruvu of Chintakani 1 No 3000.00 No 3,000.00
18 Construction of 10.00 MLD RSF at Puttakota ( V )
of Khammam ( U ) Mandla 1 No 450.00 No 450.00
19 Construction of 500 KL Clear water sump at
Puttakota Head works 1 No 58.00 No 58.00
20 Construction of summer storage tank in the bed of
Velugumatla cgeruvu of Puttakota 1 No 3000.00 No 3,000.00
21 Add 1% workers welfare cess 132.00
22 Add 5% VAT 666.00
23 Construction of Power room at Gurvaigudem Head
works L.S 9.00
24 Provision for Service line charges, Security deposite, Development Charges payable to TSNPDCL at Intake well near Palair Reservoir
145.00 25 Provision for Un interrupted Power supply & erection
of Transformer at HW 'and C/O HT yard etc. Near Intake well
215.00 26 Provision for Service line charges, Security deposite,
Development Charges payable to TSNPDCL at WTP near Gurvaigudem Head works
150.00 27 Provision for Un interrupted Power supply & erection
of Transformer at HW 'and C/O HT yard etc. near WTP at Gurvaigudem
180.00
28 Provision for SCADA arrengement 400.00
29 Provision for taxes on pipes like CED, CESS etc. 30.00
30 Provision for Land acquisition Payments to line
departments for permissions 200.00
31 Provision for price variation and other unforeseen
items 578.25
16,000.00
Telangana Water grid
DETAILED CUM ABSTRACT ESTIMATE
Name of the Sub-Work ::-Construction of 5.00 MLD Rapid sand filters at Chintakani
Sno Descirption of item Quantity Rate Per Amount
1 2 3 4 5 6
1 Construction of Rapid Gravity Filtration Plant including civil, mechanical and electrical fully automation including trial running etc., complete.
5.00 MLD Capacity with following specification
5000000 4.8852 Lit 24426000
2 Unforeseen items if any LS 574000
Total 25000000
250
Asst.Engineer Dy. Executive Engineer Executive Engineer
CPWS,Chintakani R.W.S&S, Sub division R.W.S&S, Division Madhira Khammam
Superintending Engineer R.W.S. Circle
Khammam
TELANGANA WATER GRID KHAMMAM DISTRICT
Segmant No:25 Khamma Rural Mandal
Detailed cum Abstract Estim ate for 10.00 MLD Rapid sand filters
Sno Descirption of item Quantity Rate Per Amount
1 2 3 4 5 6
1 Construction of Rapid Gravity Filtration Plant including civil, mechanical and electrical fully automation including trial running etc., complete.
10.00 MLD Capacity with following specification
10000000 4.299 Lit 42990000
2 Unforeseen items if any LS 2010000
Total 45000000
450
Asst.Engineer Dy.Exe.Engineer Executive Engineer CPWS , Edulapuram RWS & S, Sub-Division, RWS & S, Divn, Madhira Khammam Khammam Khammam
Superentinding Engineer RWS & S, Circle
Khammam.
Telangana Drinking water Grid : Khammam Dist.
Name of the Segment : Palair
Name of the Sub-Work ::-Construction of 30.00 MLD Rapid sand filters at Gurvaigudem
Sno Descirption of item Quantity Rate Per Amount
1 2 3 4 5 6
1 Construction of Rapid Gravity Filtration Plant including civil, mechanical and electrical fully automation including trial running etc., complete.
30.00 MLD Capacity with following specification
30000000 3.3023 Lit 99069000
2 Unforeseen items if any LS 931000
Total 100000000
1000
Asst.Engineer Dy. Executive Engineer Executive Engineer Superintending Engineer CPWS RWS, Sub Divn, RWS, Proj. Divn, RWS, Circle,
Palair Khammam Khammam Khammam
Telangana Drinking water Grid : Khammam Dist.
Name of the Segment : Palair
Name of the Sub-Work ::-Construction of 90.00 MLD Rapid sand filters at Jeella cheruvu for both rural areas and Khammam corporation
Sno Descirption of item Quantity Rate Per Amount
1 2 3 4 5 6
1 Construction of Rapid Gravity Filtration Plant including civil, mechanical and electrical fully automation including trial running etc., complete.as per specifications in SSr 2014-15
90.00 MLD Capacity with following specification
90000000 3.3028 Lit 297205524
3 Unforeseen items if any LS 294476
Total 297500000
2975
Asst.Engineer Dy. Executive Engineer Executive Engineer Superintending Engineer TDWSP TDWSP, Sub Divn, TDWSP. Divn, TDWSP, Circle,
Palair Khammam Khammam Khammam
Name of the work: Providing CPWSS Scheme to Krosuru and other habitations in Gundur district Abstract litre rate estimate for construction of 40000 litres, 9.60m staging OHSR at Utukuru
55.56m/sec 185.21 Amount in Rs lakhs 35.72
S.No Description Qty Rate per Amount
Construction of OHSR for finished work including 2 coats of snowcem painting, lettering, fixing of all required fixtures, pipes, bends,valves,etc. complete as per departmental designs and drawings.
Fixtures include:
1. RCC or Aluminium inside ladder 2. Dog legged staircase 3. Lightening arrestor including conductor and earthing 4. Water level indicator of good quality with ebonite/copper float, approved pattern, 5. Ventilators 6. Man hole frame and cover 2 Nos. and 7. Railing GI or RCC at floor slab level, 8. RCC hand railing alround at top of reservoir 9.MS ladder/spiral stair case on the outside M30grade
204
a Basic rate per litre 40000 34.37 litre 1374800.00
b
Add increase/decrease @5%per100kg/sqcm for wind pressure
40000 -3.12 litre -124604.00
c Add 10% for rural areas 40000 3.44 litre 137480.00
d Add for increase in staging 40000 -0.01 litre -400.00
e Add for decrease in rate of Cement 40000 -1.68 litre -67200.00 f Add for increase in rate of Steel 40000 -2.75 litre -110000.00 g Add for increase/decrease in rate wind pressure
h Provision towards cost of CI Specials and valves 1867711.00
i Provision towards const.of valve chambers 49977.00
j Provision towards unforeseen items 0.00
k Add Contractors profit @14% 418640.00
l Unforseen items & CED on CI pipes and specials LS 25935.00
Total 3572339.00
Name of the work: Providing CPWSS Scheme to Krosuru and other habitations in Gundur district Abstract litre rate estimate for construction of 60000 litres, 12.75m staging OHSR at BC ST and Kanna colonies
55.56m/sec 185.21 Amount in Rs lakhs 37.72
S.No Description Qty Rate per Amount
Construction of OHSR for finished work including 2 coats of snowcem painting, lettering, fixing of all required fixtures, pipes, bends,valves,etc. complete as per departmental designs and drawings.
Fixtures include:
1. RCC or Aluminium inside ladder 2. Dog legged staircase 3. Lightening arrestor including conductor and earthing 4. Water level indicator of good quality with ebonite/copper float, approved pattern, 5. Ventilators 6. Man hole frame and cover 2 Nos. and 7. Railing GI or RCC at floor slab level, 8. RCC hand railing alround at top of reservoir 9.MS ladder/spiral stair case on the outside M30grade
204
a Basic rate per litre 60000 26.07 litre 1564200.00
b
Add increase/decrease @5%per100kg/sqcm for wind pressure
60000 -2.36 litre -141770.00
c Add 10% for rural areas 60000 2.61 litre 156420.00
d Add for increase in staging 60000 0.06 litre 3600.00
e Add for decrease in rate of Cement 60000 -1.28 litre -76800.00 f Add for increase in rate of Steel 60000 -2.09 litre -125400.00 g Add for increase/decrease in rate wind pressure
h Provision towards cost of CI Specials and valves 1867711.00
i Provision towards const.of valve chambers 49977.00
j Provision towards unforeseen items 0.00
k Add Contractors profit @14% 439813.00
l Unforseen items & CED on CI pipes and specials LS 34589.00
Total 3772340.00
NAME OF THE WORK :: CPWS scheme to 18 tail-end saline affected habitations including Edarada in East Godawari District
Requirement of CI Specials for the OHSR with 9.55m staging
Diameter of pipe in MM 100
S.No. Description Dia. Req No's Rate Per Amount
1 Inlet connections
D/F pipes - 2m. Long 100 5 3438.97 17194.85
D/F pipes - 0.90m. Long 100 1 1815.92 1815.92
D/F pipes - 0.60m. Long 100 2 1373.26 2746.52
90 D/F bends 100 1 987.54 987.54
Tail pieces 100 1 1129.28 1129.28
Duck foot bends 100 1 1510.36 1510.36
2 Outlet connections
D/F pipes - 2m. Long 100 4 3438.97 13755.88
D/F pipes - 0.90m. Long 100 1 1815.92 1815.92
D/F pipes - 0.60m. Long 100 2 1373.26 2746.52
Bell mouths 100 1 522.82 522.82
Duck foot bends 100 1 1510.36 1510.36
3 Scour connections
D/F pipes - 2m. Long 80 4 2730.26 10921.04
D/F pipes - 0.90m. Long 80 2 1465.05 2930.10
D/F pipes - 0.60m. Long 80 4 1119.99 4479.96
Bell mouths 80 1 406.63 406.63
Duck foot bends 80 2 1219.90 2439.80
Semicircular bend 80 1 1452.27 1452.27
4 Overflow connections
D/F pipes - 2m. Long 100 5 3438.97 17194.85
D/F pipes - 0.90m. Long 100 1 1815.92 1815.92
D/F pipes - 0.60m. Long 100 2 1373.26 2746.52
Bell mouths 100 1 522.82 522.82
90 D/F bends 100 1 987.54 987.54
Tail pieces 100 1 1129.28 1129.28
Duck foot bends 100 1 1510.36 1510.36
5 Sluice Valves
Sluice valve for Inlet 100 1 8754.00 Each 8754.00
Sluice valve for Outlet 100 1 8754.00 Each 8754.00
Sluice valve for Scour 80 1 6626.00 Each 6626.00
Provision for CED for CI specials 0.00
Total 118407.00
Abstract litre rate estimate for construction of 250000 litres, 15 m staging OHBR at Jeella cheruvu Hillock for Nelakondapally and Mudigonda Mandals
200 Amount in Rs lakhs 90.00
S.No Description Qty Rate per Amount
Construction of OHSR for finished work including 2 coats of snowcem painting, lettering, fixing of all required fixtures, pipes, bends,valves,etc. complete as per departmental designs and drawings.
Fixtures include:
1. RCC or Aluminium inside ladder 2. Dog legged staircase 3. Lightening arrestor including conductor and earthing 4. Water level indicator of good quality with ebonite/copper float, approved pattern, 5. Ventilators 6. Man hole frame and cover 2 Nos. and 7. Railing GI or RCC at floor slab level, 8. RCC hand railing alround at top of reservoir 9.MS ladder/spiral stair case on the outside M30grade
204
a Basic rate per litre 250000 20.81 litre 5202500.00
b
Add increase/decrease @5%per100kg/sqcm for
wind pressure 250000 -1.72 litre -429206.00
c Add 10% for rural areas 250000 2.08 litre 520250.00
d Add for decrease in staging 250000 0.25 litre 62500.00
e Add for increase in staging 250000 0.00 litre 0.00
f Add for decrease in rate of Cement 250000 3.06 litre 765000.00 g Add for increase in rate of Steel 250000 -1.04 litre -260000.00
h Provision towards cost of CI Specials and valves 1867711.00
i Provision towards const.of valve chambers 70788.00
j Add Contractors profit @14% 1019101.00
k Unforseen items & CED on CI pipes and specials LS 181356.00
Total 9000000.00
90.00
Asst.Engineer Dy. Executive Engineer Executive Engineer Superintending Engineer TDWSP TDWSP, Sub Divn, TDWSP Divn, TDWSP, Circle, Palair Khammam Khammam Khammam
Capacity Rate 10000 58.54
15000 40.26 As per the
20000 39.56 SSR Estimate
40000 35.02 Cement 4000 6100
60000 26.57 Steel 46500 44000
80000 25.55 decrease Staging - 10 mts 10 15
90000 25.04 increase Staging - 10 mts 100000 24.53
120000 23.92
150000 23.00 1.32
200000 21.47 0.66
250000 20.81 20.81
300000 20.15
350000 18.96
400000 17.77 450000 15.40
VC for 500 mm pipe lines 54,820
VC for 80 mm pipe lines 15,968
70,788
0.00
Requirement of CI Specials for the OHSR with 15.0 m staging
Diameter of pipe in MM 100
S.No. Description Dia. Req No's Rate Per Amount
1 Inlet connections
D/F pipes - 2m. Long 450 9 32943.90 296495.10
D/F pipes - 0.90m. Long 450 0 16973.11 0.00
D/F pipes - 0.60m. Long 450 1 12617.44 12617.44
90 D/F bends 450 1 16656.20 16656.20
Tail pieces 450 1 10664.39 10664.39
Duck foot bends 450 1 25795.00 25795.00
2 Outlet connections
D/F pipes - 2m. Long 500 7 38530.36 269712.52
D/F pipes - 0.90m. Long 500 1 19941.01 19941.01
D/F pipes - 0.60m. Long 500 1 14871.19 14871.19
Bell mouths 500 1 8844.00 8844.00
Duck foot bends 500 1 32870.20 32870.20
3 Scour connections
D/F pipes - 2m. Long 250 7 13826.12 96782.84
D/F pipes - 0.90m. Long 250 2 7194.59 14389.19
D/F pipes - 0.60m. Long 250 3 5386.00 16157.99
Bell mouths 250 1 2284.70 2284.70
Duck foot bends 250 2 8180.70 16361.40
Semicircular bend 250 1 11792.00 11792.00
4 Overflow connections
D/F pipes - 2m. Long 450 9 32943.90 296495.10
D/F pipes - 0.90m. Long 450 0 16973.11 0.00
D/F pipes - 0.60m. Long 450 1 12617.44 12617.44
Bell mouths 450 1 6854.10 6854.10
90 D/F bends 450 1 16656.20 16656.20
Tail pieces 450 1 10664.39 10664.39
Duck foot bends 450 1 25795.00 25795.00
5 Sluice Valves
Sluice valve for Inlet 450 1 219588.00 Each 219588.00
Sluice valve for Outlet 500 1 235759.00 Each 235759.00
Sluice valve for Scour 80 1 7255.00 Each 7255.00
Provision for CED for CI specials 169792.00
Total 1867711.00
Asst.Engineer Dy. Executive Engineer Executive Engineer Superintending Engineer TDWSP TDWSP, Sub Divn, TDWSP Divn, TDWSP, Circle, Palair Khammam Khammam Khammam
400 KL Sump at Chintakani.xls
NAME OF THE WORK :: PROVIDING PROTECTED DRINKING WATER TO THE TRIBAL HABITATIONS IN KERAMERI, JAINUR, SIRPUR-U, AND NARNUR MANDALS IN ADILABAD DISTRICT
Abstract cum detailed estimate for Construction of Clear water Sump well of 1600 KL
Est cost in Rs lakhs: #REF!
Sl.
No .
Description No. Measurements
Qty. Rate (Rs) per Amount (Rs)
L B D
1 Earth work excavation in hard gravelly soils and depositing on bank and disposing off from the site upto 250m lead . including cost and conveyance of all materials and labour charges etc., complete as per standard specifications.
For sump Fdn. Up to 2m Depth 1x1 27.30 27.30 2.00 1490.58 #REF! 1 Cum #REF!
2m -3 m Depth 1x1 27.30 27.30 0.925 689.39 #REF! 1 Cum #REF!
2 PCC (1:4:8) using 40 mm HBG metal including cost and conveyance of all materials and labour charges etc., complete as per standard specifications for foundation
levelling course 1x1 27.30 27.30 0.30 223.59 #REF! 1 Cum #REF!
3 VRCC (1:1.5:3) using 20 mm HBG crushed metal including cost and conveyence of all materials and labour charges but excluding cost of steel and its fabrication charges etc., complete as per standard specifications for
a) Floor slab 1x1 27.300 27.300 0.325 242.219 #REF! 1 Cum #REF!
b) Inner columns 1x36 0.300 0.300 3.075 13.561 #REF! 1 Cum #REF!
c) Beams in X Direction 1x6 26.000 0.300 0.225 12.285 #REF! 1 Cum #REF!
d) Beams in Y Direction 1x6 24.200 0.300 0.225 11.435 #REF! 1 Cum #REF!
e) Side wall 350 mm Thick 1x1 105.400 0.350 1.500 55.335 #REF! 1 Cum #REF!
f) Side wall 250 mm Thick 1x1 105.000 0.250 1.800 47.250 #REF! 1 Cum #REF!
g) Haunch portion 1x1 103.000 0.250 (0.25/2) 3.219 #REF! 1 Cum #REF!
h) Roof slab 1x1 26.700 26.700 0.125 89.111 #REF! 1 Cum #REF!
4Acco-proof Plastering with CM(1:3) prop. 12 mm thick with 2% acco-proof powder including cost and conveyance of all materials and labour charges etc., complete as per standard specifications for sump well
Bottom of the sump 1x1 26.000 26.000 - 676.000
Side walls inside 1x4 26.000 - 3.300 343.200
Inner Columns 1x36 1.200 - 3.075 180.810
Beams sides 1x6 26.000 0.450 - 81.900
1x6 24.200 0.450 - 76.230
Top slab ceiling 1x1 26.000 26.000 - 676.000
Deduct for columns portion 1x49 0.300 0.300 - -4.410
2029.730 #REF! 10 Sqm #REF!
400 KL Sump at Chintakani.xls Sl.
No .
Description No. Measurements
Qty. Rate (Rs) per Amount (Rs)
L B D
5Plastering with CM(1:3) prop. 12 mm thick including cost and conveyance of all materials and labour charges etc., complete as per standard specifications for sump
well Side walls Outside above G.Lelvel 1x4 26.500 - 1.000 106.00
Over top slab 1x1 26.700 26.700 - 712.890
Total 818.890 #REF! 10 Sqm #REF!
6Snowcem painting with 2 coats over a primary coat including cost and conveyance of all materials and labour charges etc., complete as per standard specifications
Side wall Outside above GL 1x4 26.500 - 1.000 106.00
Over top slab 1x1 26.700 26.700 - 712.890
Total 818.89 #REF! 10 Sqm #REF!
7 Providing of RCC Design railing of 65mm Thick including cost and conveyance of all materials and
labour charges etc., complete L.S. 60,000
8 Provision towards cost of steel and
Fabrication charges of steel 50.00 #REF! 1 MT #REF!
9 Provision for RCC phenial as per
standard specifications 25 800 Job 20,000
10 Providing mesh to phenials including
all charges 25 300 Job 7,500
11 Provision for RCC inside ladder as
per the standard specifications 2 5000 Each 10,000
12 Supply and fixing of CI light type man hole cover with frame of size 0.6 x 0.6m as per standard
specification 4 2130 each 8,520
#REF!
14 Provision for unforeseen items such as precautions to be taken for uplift condition, refilling the foundation with excavated earth
and rock cutting, etc. L.S. 106,800
Total Rs. #REF!
Telangana Drinking Water Grid ; Khammam Dist.
Name of the Segment : Palair
Segment No.: 25.00
Mandal Chintakani
Capacity of Sump 400.00
Capacity of Sump Proposed 400.00 K.L Internal Diameter of sump well 14.00
Depth of side wall requird 2.58
Provide dead storage 0.30
Provide Free board 0.30
Total height of side wall 3.18
Side wall thickness 0.300 4.12
Side wall thickness 0.250
Side wall height above GL 0.60 Side wall height below GL 2.58
Bottom slab projection 0.30
Chord length 15.20 15.20
Thickness of top Dome
Thickness of bottom slab 0.300 Diameter of bottom slab 15.20 Diameter of C.C bed for foundation 15.80
Thickness of CC bed 0.30
Depth of excavation for foundation 3.48
Top slab dia 15.10 15.10
Top ring beam width Top ring beam depth
Radius of the circle of dome 0.00
Telangana Drinking Water Grid ; Khammam Dist.
Abstract cum detailed estimate for 500 KL capacity sump at Chintakani
Est Cost in Rs Lakhs: 40.00
Sl. Description No. Measurements Qty. Rate per Amount
No. L B D (Rs) (Rs)
1 Earth work excavation in hard gravelly soils and depositing on bank with an initial lead of 10 m.
and lift of 2 m. including cost and conveyance of all materials and labour charges etc.,
complete as per standard specifications.
For Foundation 0.00 to
3.00 Mts. 0.785 15.80 15.80 3.00 587.90 122.40 1 Cum 71,959
For Foundation 3.00 mts.
6.00 mts. 3.000 1.50 1.20 0.50 2.70 157.40 1 Cum 425
2
Filling of sand in the bed of the foundation including cost and conveyance of all materials and labour charges etc., complete as per standard specifications.
For Foundation 0.785 15.80 15.80 0.30 58.79
For Foundation 4.000 1.50 1.20 0.30 2.16
60.95 2182.50 1 Cum 133,023 PCC (1:3:6) using 40 mm HBG metal including
cost and conveyance of all materials and labour charges etc., complete as per standard specifications for foundation levelling course
For Foundation 0.785 15.80 15.80 0.30 58.79
For Foundation 4.000 1.50 1.20 0.30 2.16
4 60.95 5088.10 1 Cum 310,120
4 VRCC (1:1.5:3) using 20 mm HBG crushed metal including cost and conveyence of all materials and labour charges but excluding cost of steel and its fabrication charges etc., complete as per standard specifications for
For Floor Slab 0.785 15.20 15.20 0.450 81.61 8663.00 1 Cum 706,987
For Wing slabs 4 1.50 1.00 0.300 1.80 8663.00 1 Cum 15,593
For side wall 300 mm Thick 3.142 14.30 0.30 1.80 24.26 12003.90 1 Cum 291,215 For side wall 250 mm Thick 3.142 14.25 0.25 1.61 18.02 12774.50 1 Cum 230,196
For Columns 21 0.30 0.30 3.11 5.88 10366.90 1 Cum 60,957
Sl. Description No. Measurements Qty. Rate per Amount
No. L B D (Rs) (Rs)
For beam I 2 14.50 0.30 0.30 2.61
For beam II 4 14.00 0.30 0.30 5.04
For beam III 4 12.70 0.30 0.30 4.57
Deduct beam Junctions 21 0.30 0.30 0.30 -0.57
11.65 10448.70 1 Cum 121,727
Haunches 3.142 14.85 0.23 (0.225/2) 1.21 8663.00 1 Cum 10,482
For topslab of 150mm
thick 0.785 15.10 15.10 0.150 26.85
Deduct Manholes 4 0.60 0.60 0.150 -0.22
Deduct Ventilators 2x0.785 0.90 0.90 0.150 -0.19
26.44 9514.70 1 Cum 251,569 6 Plastering with CM(1:3) prop. 12 mm thick
including cost and conveyance of all materials and labour charges etc., complete as per standard specifications for sump well
Outside the sump 3.142 15.50 0.90 43.83
Columns alround 21 1.20 3.10 78.12
Sides of the beams I 2 15.00 0.30 9.00
Sides of the beams I2 4 14.00 0.30 16.80
Sides of the beams 3 4 12.70 0.30 15.24
Deduct beam junctions 2x2 0.30 0.30 -0.36
Ceiling of the top slab 0.785 14.00 14.00 153.86
Total 316.49 2147.50 10 Sqm 67,966
7 Acco-proof Plastering with CM(1:3) prop. 12 mm thick with 2% acco-proof powder including cost and conveyance of all materials and labour charges etc., complete as per standard specifications for sump well
Inside side wall of sump 3.142 14.00 3.40 149.56 Bottom of the sump 0.785 14.00 14.00 153.86
Total 303.42 1560.60 10 Sqm 47,352
8 Snowcem painting with 2 coats over a primary coat including cost and conveyance of all materials and labour charges etc., complete as per standard specifications
Outside above GL 3.142 15.50 0.90 43.83
Over the slab 0.785 15.10 15.10 178.99
222.82 964.30 10 Sqm 21,487
Sl. Description No. Measurements Qty. Rate per Amount
No. L B D (Rs) (Rs)
9 Provision towards cost of steel and fabrication
charges 21.50 60898.80 1 Mt 1,309,324
10 Provision for G.I. pipe railing around the top
slab 3.14 14.25 44.75 650.32 1 Mtr. 29,102
11 Provision for RCC central phenial as per standard
specifications 2 2000 Each 4,000
12 Providing mesh to phenials including all
charges 2 1500 Each 3,000
13 Provision for RCC ladder inside the sump as per
the standard
specifications 1 4000 Each 4,000
14 Supply and fixing of RCC manhole cover of size
0.9mx0.9m as per standard specification 2 1500 each 3,000
15 Provision for pipe line from RSF Out let to sump and inlet connections to sump etc. with c.I. D/F
pipes, specials, valves . 1
As per sub
Esimate 249,347
16 Add L.S for toher
unforeseen items 129,553
4,000,000 40.00
Asst.Engineer Dy.Exe.Engineer Executive Engineer RWS & S, Chintakani RWS & S, Sub-Division, RWS & S (Proj,) Divn,
Madhira Khammam
Superentinding Engineer RWS & S, Circle