Infrastructure Development in DEI
(Last 5 years – 2012 to 2017)
Infrastructure Development ( last five years - 2012 to 2017 )
S. No. Name of Building Built - up Area Date of Source of Completion
(sq.meters) Completion Funds Cost
1 Women's Hostel ( Ground Floor ) 2128 22.02.2012 UGC (XI plan) 129.17 lacs
2 Women's Hostel ( First Floor ) 1866 28.02.2013 UGC (OBC) 141.97 lacs
3 Work's Department 805 28.02.2013 UGC (OBC) 105.91 lacs
4 Extn. Of DES Block 135 30.12.2013 UGC (OBC) 19.91 lacs
5 Extn. of Library (Faculty of Engg.) 486 15.02.2014 UGC (OBC) 80.04 lacs and UGC ( XI
plan)
6
Seminar Hall Complex cum
Continuing 1232 10.03.2014 UGC (OBC) 367.56 lacs
Women’s Hostel (Ground Floor)
Built - up Area 2128 sq.meters
• Date of Completion 22.02.2012
• Source of Funds UGC (XI Plan)
• Completion Cost 129.17 lacs
Women's Hostel ( First Floor )
• Built - up Area 1866 sq.meters
• Date of Completion 28.02.2013
• Source of Funds UGC (OBC)
• Completion Cost 141.97 lacs
Women’s Hostel - II
Work’s Department
• Built - up Area 805.00 sq.meters
• Date of Completion 28.02.2013
• Source of Funds UGC (OBC)
• Completion Cost 105.91 lacs
Works Department
Extn. Of DES Block
• Built - up Area 135.00 sq.meters
• Date of Completion 30.12.2013
• Source of Funds UGC (OBC)
• Completion Cost 19.91 lacs
Hall in DES Block (First Floor)
Extn. Of Library (Faculty of Engg.)
• Built - up Area 486.00 sq.meters
• Date of Completion 15.02.2014
• Source of Funds UGC (OBC) and UGC (XII Plan ) Completion Cost 80.04 lacs
Extn. Of Library ( F. o.Engg. )
Extn. Of Library ( F. o.Engg. )
Seminar Hall Complex cum
Continuing Education Faculty Hostel
Built - up Area 1232.00 sq.meters Date of Completion 10.03.2014
Source of Funds UGC (OBC) and UGC (XI Plan) Completion Cost 367.56 lacs
Seminar Hall Complex
Seminar Hall Complex
Extn. Of Botany Department
• Built - up Area 311.00 sq.meters
• Date of Completion 20.03.2014
• Source of Funds UGC (XI-Plan)
• Completion Cost 40.01 lacs
Extn. Of Botany Department Building
Extn. Of Multimedia
• Built - up Area 486.00 sq.meters
• Date of Completion 31.08.2014
• Source of Funds UGC (OBC)
• Completion Cost 222.16 lacs
Extn. Of Multimedia Building
Information and Communication Technology Building
• Built - up Area 1187.00 sq.meters
• Date of Completion 22.08.2015
• Source of Funds UGC (OBC) Completion Cost 209.87 lacs
Information and Communication
Technology Building
Multipurpose Gymnasium
• Built up Area - 702.00 sq.meters
• Date of Completion - under construction
• Source of Funds - 1.0 crores (UGC)
Balance – own resources Expected Completion Cost – 148.55 lacs
Multipurpose Gymnasium
Bamboo Creche
• Built up Area 369.00 sq. Meters
• Date of Completion under construction
• Source of Funds Non Govt. Funds
• Expected Completion
Cost Rs. 73.40 lacs
Bamboo Creche
Miscellaneous Works
• Ramps for the aid of handicapped and old persons have been added in all the buildings.
• Water Harvesting wells have been provided at various low lying places which help in harvesting most of the rain water.
• Roads of the Institute have been repaired and provided with a layer of premix Bituminous Carpet
• Separate Toilet blocks for boys and girls have been provided in all the Faculties.
Ramps
Additions and Alterations
Main Buildings renovated are :- 1. Erstwhile Tannery Complex 2. DEI Dairy
3. DEI Shop
4. Hall for B Voc Apparel Design
Erstwhile Tannery Complex
• Our erstwhile Tannery Complex having
covered area of 2697.00 sq.meters have been renovated with minor additions and
alterations. It now houses various departments like –
• Distance Education
• CART
• Footwear Technology
• Renewable Energy (under B Voc courses)