Pre- Bid Query Clarifications for
T App Folio TELANGANA STATE m- Governance Project
Ref : TSTS/CS/ESD-mGoV/2016 Dt 26.09.2016 Date : 13-10-2016
ESD, Department of ITE&C, Government of Telangana
Page 1 of 105 o Volume No.
1 General NA Team
Deployment model
NA We understand that since the helpdesk team is deployed onsite by ESD, our support team can be completely offsite. Please confirm.
Refer to RFP, for onsite manpower requirement
2 General NA Team
Deployment model
NA If the support team is required offsite, team will be provided with VPN connectivity and dedicated internet bandwidth to connect to data-center
Connectivity will be provided as required
3 General NA Team
Deployment model
NA If the support team is required onsite, all infrastructure requirment like seating space,
laptop/desktop, telephone, internet connectivity will be provided by ESD. Please confirm.
ESD to provide seating space on need basis
4 General NA Team
Deployment model
NA If the support team is required onsite, then the entire team will be located at one central location and will not be seggregated into different offices of ESD.
Please confirm
ESD to provide seating space on need basis
Page 2 of 105
5 General NA Support Model NA Please confirm whether
1. Full Support is required for 24*7 support window Or
2. Full Support is required in general shift (Monday to Friday, 9am to 6pm) and 24*7 support can be made available for critical (Severity 4) issues only. In this case, support team can be available on call, remotely for Severity 4 issues. Helpdesk team for such issues can connect with support team on-call
Full Support is required in general shift (Monday to Friday, 9am to 6pm) and 24*7 support can be made available for critical (Severity 4) issues only. In this case, support team can be available on call, remotely for Severity 4 issues. Helpdesk team for such issues can connect with support team on-call
6 General NA Change
Management
NA We understand that for any changes in the system, the same will be subject to Change Management process at actuals.
Refer to Volume 3, Clause 55, Page number 40
& 41
7 General NA NA NA Any guideline on where to host the mobile app post
production deployment? i.e. on public app stores like Android/iOS/Windows or on customer's private app stores? This is basically required to distribute the apps to the identified users.
Upon certification, The app to be deployed on all the operating systems mentioned in the RFP (apps store / play store for citizen to download)
8 General NA NA NA Is there any hardware integration like printer, scanner, etc. is required for mobile app?
Not envisaged at this moment
Page 3 of 105
9 General NA NA NA Any guidelines on Offline capability/access of the
mobile apps? If yes, please provide the use cases?
ESD / PMU in discussion with user
departments will finalise the requirements on a need basis
10 Volume 1
3. Project Objectives
Services delivery through Smart phones as well as feature phones
8 Can we assume that the mobile application scope is limited to smart phones only?
RFP clearly mentions support for smart phone and feature phone - the features to be made available depend on the capabilities of the device.
11 Volume 1
3. Project Objectives
Supports all the standard mobile OS like
iOS/Windows/An droid/Tizen etc
8 Can we assume the mobile application will be developed for the most popular and widely used platforms -Android, iOS and Windows only with following versions of Smart phones and tablets:
Smartphones iOS 4.x and higher Android 2.1 and higher Windows Phone 7 and higher Tablets
iOS 4.x and higher Android 2.1 and higher Windows 8 & higher
It should work on all
iOS/Windows/Android/Tizen devices with the versions of Operating Systems released by them in last three years from the date of work order and all future releases
12 Volume 1
3 3. Project
Objectives
8 Tizen OS is an emerging Operating System and represents a very insignificant market share with very limited know-know how on
Please refer to Corrigendum / Addendum 13 Volume
1
2 - 8 Within 499 services how many SMS, IVRS,
USSD, Smart Client, Mobile APP and Mobile Web compatible Services.
The RFP has clearly mentioned the
requirement and ESD - PMU to decide jointly on the implementation requirements
Page 4 of 105 14 Volume
1
3 3 9 Which platforms need to be supported through
hybrid/native mobile apps and which through mobile web? Clear cut definition of the platforms which need to be supported should be provided.
ESD to decide the channels to be enabled for various services, the app is to be a native app unless explicitly agreed in writing by ESD
15 Volume 1
3 3 9 • Do the mobile applications need to be native or
hybrid?
• Can we use a MADP platform like IBM MobileFirst or Kony?
Native is the preference, Bidder to justify any other method used. ESD's decision prevails.
16 Volume 1
3 3 9 Is it mandatory to support Tizen OS for mobile apps Please refer to Corrigendum / Addendum 17 Volume
1
3 3 9 Is there any preference for mobile app type –native
VS hybrid ?
Native is the preference, Bidder to justify any other method used. ESD's decision prevails.
18 Volume 1
3. Project Objectives
Implementing Agency IA to continue to support for a maximum period of 6 months without any change in terms and conditions.
9 Please change the conditions as mentioned below:
Acceptable for max. 3 months; post which, MeeSeva shall organize a Technical and Commercial Meeting with the Vendor for further extensions to examine amendments needed in Commercial T&Cs as may be applicable at that point of time on factors such as regulatory/statutory reforms as per GOI and GOTS.
Please refer to Corrigendum / Addendum
Page 5 of 105 19 Volume
1
3. Project Objectives
Provide Mee Seva, eSeva, SSDG, eDistrict services through mobiles
9 How many mobile apps are required to be developed?
Who are stake holders/users/actors for the mobile apps? As of now it is understood that only the citizens will use the mobile apps - Please confirm if the same is true else provide the details.
As per RFP
20 Volume 1
3. Project Objectives
Provide Mee Seva, eSeva, SSDG, eDistrict services through mobiles
9 Mobile App Type Hybrid/Native
Can we consider the hybrid mobile app with all the required native features and which will be common and easy to maintain mobile app for all the required platforms (i.e. android, iOS and Windows); in place of separate native mobile apps for all the required platforms?
Native is the preference, Bidder to justify any other method used. ESD's decision prevails.
21 Volume 1
3. Project Objectives
Provide citizen centric services which are of public
importance by on boarding apps developed by private developers subject to terms and conditions
9 Can you please elaborate this requirement? An example of the same will also do.
Refer to Annexure - 4 , Volume -1 for examples
22 Volume
1 3 - 9 Why Tizen OS ? Its products are not at least
5% in market
Please refer to Corrigendum / Addendum
Page 6 of 105 23 Volume
1
4 ESD may extend
the contract after 3 years, by 1 year at a time for 2 years subject to a maximum of 10%
increase per year in the
commercials.
9 In case of extension , the prices would be re negotiable at that time
As per RFP
24 Volume 1
4 In case there is delay by ESD in selecting a new Implementing Agency IA at the end of 3 years and ESD does not wish to continue with the
Implementing Agency IA ESD has a right to ask the existing Implementing Agency IA to continue to support for a maximum period of 6 months without any change in terms and conditions.
9 The prices for the six month would be negotiable at time of asking such support
Please refer to Corrigendum / Addendum
Page 7 of 105 25 Volume
1
Mobile App /
Mobile Internet integration with MSDG platform to be done only through well- defined / well documented APIs, which is necessary for creating m-folio
10 Can you please elaborate on what is m-folio? Govt of Telengana plans to enable other department services as well as private services on the platform, the user need to be able to access these services from the mobile governance app - the aggregation of these services is called m-folio
26
Volume
1 6 10
IVR details required.
1. How many langauges required in IVR 2.Sample IVR call flow to be included
3. do you need IVR and SMS gateway integration, pleae provide the number of channels required.
4. list us IVR backend integration required?
Refer to Volume 1 , Section 8.7
Page 8 of 105 27
Volume
1 6 10
Unified Communiction Module
1. Do you existing UCM module or IA to propose the UCM setup
2. Total number of extension required in UCM setup 3. Total number of Trunks required in UCM setup 4. what is the UC and mobile application integration 5. number of locaiton for UC setup
6. Provide Technical specification for UC setup
Bidder to suggest with justification
28 Volume 1
6.5 Marketing and promotions module
12 Promotions for ESD will result in cost to IA in terms of SMS/VAS costs. These are not covered under
transactional revenues. Will additional payments be made for these campaigns or does the IA have to bear the costs?
As per RFP, Refer Volume 1, Section 10.4
Page 9 of 105 29 Volume
1
Section 6.8.
Remote Applicatio n
Monitorin g (RAM)
Mobile service delivery platform is going to have multiple loosely coupled modules to facilitate scalability and management of the platform. The platform needs to have high availability and load balancing built into it
13 Query - Are we talking about high availability of all components including DB layer associated with the m- Governance project .Please clarify.
The platform need to run in high availability mode to avoid single point of failure. The IA is expected to provide the necessary
deployment and application architecture to meet this requirement
30 Volume 1
6.9. MIS Reporting and Dashboard
MIS Reporting and Dashboard
13 Does the report access is envisaged on the mobile app also? If yes, how many such reports can be envisaged?
Access of reports is required from Desktop / Laptop / Smartphone
31 Volume 1
6.6 - 13 semi-closed wallet is provided by ESD or its responsibility of IA
Payment Instruments to be decided by ESD
32 Volume 1
6.8 Remote
Application Management
13 RAM can be provided from SDC or remotely. But remote management requires a secure connection to SDC Servers. Will ESD provide such remote access to IA nominated executives?
ESD to provide required access
Page 10 of 105 33 Volume
1
7.1 Mobile Ecosystem
Application Architecture
14 What is the difference between SI/Platform Vendor and Mobile App Company?
SI - Systems Integrator(Implementation Agency)
Platform Vendor - MSDG Platform Provider (OEM)
Mobile App Company - Company developing mobile applications
34 Volume 1
6.8 14 Remote Application Monitoring (RAM)
Whether the department is looking for monitoring and management of all individual applications integrated with MSDG gateway and trigger events as sson as any service is down. If yes, then this falls under the category of EMS APM module, which definitely will have steep cost implications.
Even APM application cannot work here because all APM application needs Agents to be deployed on independent Application Modules of each department.
Each individual applications should expose the application health/availability webservice.
Primary requirement is to manage MSDG platform and the APIs integrated with MSDG platform.
Monitoring of Individual applications are done by respective departments.
Page 11 of 105 35 Volume
1
7.1 Mobile Ecosystem
• 3rd party developers / organizations - – ITE&C
department desires to involve 3rd party
developers / organizations to build innovative, user friendly applications for the any services offered through T App Folio. MSDG platform must factor in this and shall have all the necessary functionalities to ensure secure on boarding of these applications.
16 Can you please elaborate this requirement? An example of the same will also do.
Refer to Annexure - 4 , Volume -1 for examples
36 Volume 1
7.1 3rd party developers
16 It is assumed that IA will provide only the portal and API services for integration to Govt Dept services. 3rd party developers have to use these services to develop
mobile apps, get them vetted and onboard them onto MSDG AppStore. Mobile App development is not in the scope of this project. Please confirm.
As per RFP, Refer Volume 1, Section 7.1, Section 9.3 and other related sections
Page 12 of 105 37 Volume
1
7.2.
Service Categoriza tion
5. ESD intends to provide
Informational and other non- payment services to its residents free of charge. As there will be no revenue
generated out of these
Informational and other non- payment services IA is not entitled for any payment on these
category of services.
17 Can you please elaborate this requirement? An example of the same will also do.
Refer to Volume 1 , Section 7.2 for examples
38 Volume 1
8.1 Cloud Technolog y
It is important for the services and application to be cloud ready, to take the advantage of next generation cloud
implementations and technologies.
18 Please clarify if Cloud Solution can be proposed or it will be hosted at State DC?
To be Hosted in State DC
Page 13 of 105 39 Volume
1
7.2.
Service Categoriza tion
Number of Services to be Enabled
&
Number of Informational and non-payment Services to be Enabled
18 Can we assume that these services will be enabled post Go-Live and will be a part of support?
How many services are required to be made live during Go-Live? Please elaborate.
All the services which Go-Live will be the part of the support.
40 Volume 1
8.7. Multi- Lingual Support
The IA shall support for English, Telugu and Hindi languages across various channels (SMS, IVR, USSD, Smart Client, Mobile Web etc.) for services across service categories as required by Government of Telangana.
19 Can we assume: only application labels and static contents will be made available for the selected languages while the data entry will be limited to English language only.
Application labels and static content to support multiple languages, data entry support depends on the department capabilities - to be decided on case to case basis
41 Volume 1
8.9.
Performan ce/Scalabil ity
c. Single point of bottle-neck and failure must be avoided
20 Please confirm that the solution at DC will be in Active - Active scenario.
Bidder to suggest solution to meet project requirements
Page 14 of 105 42 Volume
1
Section : 8.10.
Security Level
The platform needs to have capability to manage security and privacy at multiple levels. A transactional service may require higher security levels than an ordinary information service such as status check or weather forecast.
Non-functional requirements such as data security, user authorization and access control need to be taken into account while designing the platform
20 Query - Are we talking about role based
authentication/authorization, Role-Based Access Control,
Authentication as required by the User Dept.
with the ability to connect to external server like Aadhaar for authentication, role based access control in the portal may be required
43 Volume 1
Section:
8.9.
Performan ce/Scalabil ity
Single point of bottle-neck and failure must be avoided
20 Query – Is active active clustering is considered for the entire m- Governance Project including DB.
Bidder to suggest solution to meet project requirements
Page 15 of 105 44 Volume
1
8.13 20 From the given RFP document looks T-Government
expects Service Delivery model in opensource technologies.Hence can we suggest solution on opensource technologies only?
Refer to Volume 1, Section 8.13
However, Bidder should justify his approach for selection of technology along with associated Risks and Benefits.
45 Volume 1
7 7.13 Open Source 20
Open Source is known for its vulnerability at multiple levels - Lack of Product Roadmpap, Dependency on Open Communities for new Code Development, Limited or Lack of Proactive Security threats, and Excessive maintenance requirement for the code written. In Comparison OEM provisioned products which are security hardened, tested for scalability, and has required commitment on Support. Request the Department to kindly consider OEM solutions for this prestigious projects
Refer to Volume 1, Section 8.13
However, Bidder should justify his approach for selection of technology along with associated Risks and Benefits.
46 Volume 1
8 8.11 21 Which platforms need to be supported through
hybrid/native mobile apps and which through mobile web? Clear cut definition of the platforms which need to be supported should be provided.
Native is the preference, Bidder to justify any other method used. ESD's decision prevails.
Page 16 of 105 47 Volume
1
8.16.
Avoiding Device Vendor Lock-in
Vendor is required to evaluate the technology platform to be used for
development of the mobile application, any technology platform which would result in vendor lock-in must be avoided at any cost.
21 Many state government are using industry leading Mobile Application Development Platforms (MADPs) for services offering or for providing citizen services through mobile. Can we go ahead and adopt the same (i.e. enterprise grade MADPs...)?
As per RFP
48 Volume 1
8 8.16. Avoiding
Device Vendor Lock-in
21 "In case vendor develops the mobile app using a framework, that framework must be made available even after the expiry of the agreement for ESD to use, at the same time, vendor must provide sufficient explanation to for use of one method over other (Ex.
native application versus mobile app developed using framework)"Only In case of Standard OEM offerings the state is insulated from Code-Level Vendor Lockin or Platform Lockin. The State Govts. investments will be protected if OEM offerings with standard support committment, product roadmap, expiry terms, etc are available. No customer vendor developing on Open Source can committ this as 'Custom Development' and 'Open Source' are receipes for uncertainity. Kindly consider mandating OEM products for this RFP.
Bidder is encouraged to consider associated risksand propose solution to ESD with justification
Page 17 of 105 49 Volume
1
9.1.
Mobile Services Delivery Gateway (MSDG)
c. Deployment, maintenance &
monitoring of application servers, database server and other related servers at primary and DR site relating to MSDG.
22 Please clarify what will be the DR size. Will it be 100%
od DC or 50% of DC.
Bidder to suggest solution to meet project requirements
50 Volume 1
9.1.
Mobile Services Delivery Gateway (MSDG)
e. Create and manage UAT (User Acceptance Testing) setup for MSDG. The UAT setup shall be near replica of the production setup, ESD (Mee Seva) and IA to work together to decide the configuration of the setup
22 Please clarify the "near replica". We understand that all the s/w proposed for DC has to be proposed for UAT setup. The quantity may differ.
Bidder to suggest minimum requirement for UAT setup
Page 18 of 105 51 Volume
1
Section 9.1 Deployment, maintenance &
monitoring of application servers, database server and other related servers at primary and DR site relating to MSDG.
22 Query - About DB requirement for DC and DR.I understand yes its required .But please clarify .Also if Telenagana ITENC department will provide necessary DB licenses for this project for DC and DR .Please clarify
The cost should include all the licenses
including DB associated with MSDG both at DC
& DR
52 Volume 1
Section:
9.1.
Mobile Services Delivery Gateway (MSDG)
Manage
application, data and server security of the MSDG platform
22 Query - Are we talking about role based
authentication/authorization, Role-Based Access Control,
The portal access need to be role based access control
53 Volume 1
9.1.
Mobile Services Delivery Gateway (MSDG)
i. On-going enhancement of the core platform by implementing new features, enabling newer technologies to meet
Government of Telangana’s mobile governance objectives
22 Please elaborate on the requirement of new features, new technologies, etc. Will it be a part of Support/CR?
Any changes / enhancements to MSDG platform features mentioned in the RFP will be part of AMC
Page 19 of 105 54 Volume
1
9.3.
Mobile Applicatio n Store (MAS)
23 What is this requirement about? Is it related to private app stores for the customer and hosting various mobile apps on it? Please explain?
Is there any existing app management licenses?
As per RFP Volume 1, Section 9.3
55 Volume 1
9 9.2. Integration Layer and APIs
23 As we are talking of integration of various applications and interfaces from different channels and API would be one of the primary ways for integration, it is imperative that there is a dedicated security gateway and a Platform to create, run, manage and secure APIs. It is highly recommended that we have a complete integrated platform for Integration and Rapid Automated Creation of APIs.
API's between the MSDG & Departmental applications will be the responsibility of ESD API's between the MSDG & Mobile App Users will be the responsibility of Bidder
56 Volume 1
9.5 Support 24 It is mentioned that "Helpdesk identified by ESD to provide Level 1 support". We wanted to understand that whether this Helpdesk (that will be deployed by ESD) be operational 24*7?
As per RFP
57 Volume 1
9.5 Support 24 It is mentioned that "Helpdesk identified by ESD to provide Level 1 support". We wanted to understand that what all would be covered in L1 services - a. Providing functional and business support in regards to the processes deployed on the platform?
B. Handling calls on “How To” and “System Awareness”
c. basic issues like user creation, privileges, password resets and application navigation
d. Support based on pre-defined FAQ’s and SOP’s e. Periodic follow-up with end-user and support team on updates on open tickets / pending for user
response
Bidder may assume all the possible helpdesk scenarios
Page 20 of 105 58 Volume
1
9.3 24
Kindly clarify where to host the App store and who will bear the hosting charges
Application will be hosted in the App Stores and Software Code will be stored in SDC.
ESD to bear Hosting charges 59 Volume
1
9.9.
Setting up and managing MSDG platform in DC &DR Center
d. RTO (Recovery Time Objective) and RPO (Recovery Point Objective) shall be as per Govt. of Telangana DR Policy.
25 Please let us know the RTO and RPO for this project. DC/DR policy discussion is under progress ESD will publish the RTO and RPO details when ready.
60 Volume 1
Section 9.9 a
Deployment and management of MSDG platform and services at DC &DR center.
The DC & DR center will be made available by Government of Telangana
25 Query - About DB requirement for DC and DR.I understand yes its required .But please clarify .Also if Telangana ITENC department will provide necessary DB licenses for this project for DC and DR .Please clarify
The cost should include all the licenses
including DB associated with MSDG both at DC
& DR
Page 21 of 105 61 Volume
1
Section 9.9 b
Responsible for performance and scalability of the platform at DC
&DR Center, the list of services and channels to be
operationalized at the DR location to be provided by Government of Telangana
25 Query - About DB requirement for DC and DR.I understand yes its required .But please clarify .Also if Telenagana ITENC department will provide necessary DB licenses for this project for DC and DR .Please clarify
The cost should include all the licenses
including DB associated with MSDG both at DC
& DR
62 Volume 1
Section 9.9 c
IA is required to recommend the complete BOM for DC &DR as a part of their bid
25 Query - About DB requirement for DC and DR.I understand yes its required .But please clarify .Also if Telenagana ITENC department will provide necessary DB licenses for this project for DC and DR .Please clarify
The cost should include all the licenses
including DB associated with MSDG both at DC
& DR
63 Volume 1
9.9 d) RTO (Recovery Time Objective) and RPO (Recovery Point Objective) shall be as per Govt. of Telangana DR Policy.
25 Please share Govt. of Telangana's RPO & RTO policy DC/DR policy discussion is under progress ESD will publish the RTO and RPO details when ready
Page 22 of 105 64 Volume
1
9.9 d) RTO (Recovery Time Objective) and RPO (Recovery Point Objective) shall be as per Govt. of Telangana DR Policy.
25 Share the location of DC & DR, and the bandwidth available between these 2 locations.
DC-Hyderabad, DR location & bandwidth is Yet to be decided
65 Volume 1
2.
Infrastruct ure for SMS, IVRS, USSD
ii. ESD shall make available the recommended Hardware at DC and DRC accordingly
26 Please explain what is DRC? Is is DR? DRC is Disaster Recovery Center
66 Volume 1
10.2 Infrastructure 26 What is the data size to be expected on DC and rate of change of data per day ? What will be the expected database size for all the applications?
ESD to provide H/W, bidder is expected to make reasonable assumption wherever needed
67 Volume 1
10.2 Infrastructure 26 Is there any data migration or application migration from existing infra to the new infra in the IA's scope ?
No
68 Volume 1
10.2 Infrastructure 26 Any existing infrastructre integration required ? As per RFP
Page 23 of 105 69 Volume
1
10.1 10.1. Payments model
26 The Payment Guidelines does not link or relate any material supply (hardware or software or Open source tool support). There is no incentive for a System Integrator to be using best of breed solutions or solutions with formal product support. For stability, and efficiency considerations - request department to link payments to:1. Supply of Material2. SLAs of Installation & Configuration
As per RFP
70 Volume 1
9.9 C 26 Please provide total number of users/concurrency
expected.
This would enable us to size the required infra components
As per RFP Volume 1, Section 12 (Transaction Volume for ESD & VAS Services)
For Concurrency, Bidder is expected to make necessary assumptions based on the
Transaction volume 71 Volume
1
10.
Business model
10.1 Payment terms
50% of the platform cost to be paid upon successful Go- Live
27 As per Volume 3 section 1.1.18 definition of "Go-live", date is dependent on launch date. Launch date will in- turn be announced by government (as per 1.1.17) when it deems appropriate. This clause means that no payments will be made till up to 4 months after the government officially launches the service. As
government launch date announcement is not in control of the vendor, the clause should be suitably modified to atleast release a portion of payments at various mile stones like requirement finalization, UAT acceptance etc. We request you to review the payment terms and modify accordingly
Please refer to Corrigendum / Addendum
72 Volume 1
10.2 Infrastuctu re
Hardware at DC
& DR site
27 Please specify the proposed locations of DC & DR sites DC - Hyderabad
DR location is yet to be decided
Page 24 of 105 73 Volume
1
10.2 Infrastuctu re
2. Infrastructure for SMS, IVRS, USSD
27 IVRS typically require signalling or media telephony cards (along with servers) to connect to the operator PRI/ISDN lines. Please confirm if ESD will procure even the telephony cards if they are specified in the BOQ by the selected bidder?
Bidder to provide BOM, ESD to procure the same
74 Volume 1
10 10.2 27 The solution may involve use of 3rd party software.
Who will own the cost of those licences and renewals.
It will involve DB, OS, Analytics tools etc.
Bidder to bid basis the total cost of software including licenses
Page 25 of 105 75 Volume
1
10.1 10.1. Payments model
1. Bidder should propose the MSDG platform as per the Technical requirements specified in the RFP.
2. ESD shall release the payment as follows:
a. 50% of the platform cost to be paid upon successful Go- Live
b. Remaining 50%
to be paid 6 months after Go- Live
c. Payment of MSDG AMC cost in Quarterly Installments after one year from the Go- live date.
d. Payment of service charges for transactions will be on quarterly basis.
27 Request to change the payment model as below I. Payment of MSDG Platform license Fee
a) 100% Payment for Licenses should be released upon delivery.
b) For other services during Implementation phase:
- 15% payment on SRS signoff - 30% payment on start of FAT
- 55% payment upon completion of FAT or Go Live.
NOTE: All payments will be due at the end of the quarter (April – June, July –September, October – December, January – March)
II. Payment of MSDG AMC cost
a) Quarterly Instalments after the Go live date.
III. Payment of Service Enablement of Mee Seva and VAS services Transaction Revenue Basis
a) IA to receive quarterly payment for the Transaction Revenue earned after deducting penalties, if any b) IA to submit invoices along with the supporting documents on Quarterly basis
Please refer to Corrigendum / Addendum
Page 26 of 105 76 Volume
1
10.2 27 Who will be providing the softwares (OS , DB , Application Middleware )
Software to be provided by Bidder 77 Volume
1
10.1 ESD shall release the payment as follows:a. 50% of the platform cost to be paid upon successful Go- Liveb. Remaining 50% to be paid 6 months after Go- Livec. Payment of MSDG AMC cost in Quarterly Installments after one year from the Go- live date.d. Payment of service charges for transactions will be on quarterly basis
27 It is recommended to change the payment terms as mentioned below, because RFP terms are not favorable to TCS.- 100% payment for Hardware and Software on delivery and Installation.- 100% payment for Implementation Services till Go-live- 100%
payment of training cost upon completion of training- 100% payment for Data Migration upon completion of migration- 100% payment for Site preparation upon completion of sites- Payment for Infra O&M as equated quarterly installment in Advance- Payment for Services O&M as equated monthly installment in Arrears.
Please refer to Corrigendum / Addendum
Page 27 of 105 78
Volume
1 10.5 28
What is existing HELPDESK, what type of integration is required in Helpdesk
1. What is the toltal number of Agents in Helpdesk 2. What type of agents required inbound/Outbound 3. email/chat agents are required, if required pleae provide more details
4. Does IA shold provide manpower for call centre operations
5. if IA should provide manpower for call centre, can it be outsourced
Refer to Volume 1 , Section 10.5 & 6.12
79 Volume 1
10.3, 4(iii) 28 Minimum Number of transaction should be
guaranteed for calculation of charges against Service Enablement
As per RFP
Page 28 of 105 80 Volume
1
10.2 For the purpose of clarity: IA is only required to suggest the Bill of Material for the MSDG platform, ESD to take the responsibility for procuring the same. If the infrastructure in production environment within the mentioned volume is significantly different from what is quoted in the bid,
additional hardware cost will be charged to the bidder and deducted from the payments due.
28 Request to modify the clause as below:For the purpose of clarity: IA is only required to suggest the Bill of Material for the MSDG platform, ESD to take the responsibility for procuring the same. If the infrastructure in production environment within the mentioned volume is significantly different from what is quoted in the bid, additional hardware cost will be charged to the bidder will be mutually discussed and deducted from the payments due.
As per RFP
Page 29 of 105 81 Volume
1
10.2 If the
infrastructure in production environment within the mentioned volume is significantly different from what is quoted in the bid,
additional hardware cost will be charged to the bidder and deducted from the payments due.
28 Kindly elaborate on this The Bidder is encouraged to provide sizing
based on the indicative transactions provided in Volume 1 , Section 12
82 Volume
1 10.7 - 29 Three (03) Full time Resources but other team
strength and resource cost not included
ESD requires 3 fulltime resources on premises.Bidder is free to assume other resource requirements and accordingly cost
Page 30 of 105 83 Volume
1
11.1TSTS TSTS will also work on
empanelment of Mobile
Application Developers so as to Facilitate and provide
handholding support to individual departments for on-boarding and API integration.
30 Can you please explain the role of mobile application developers enablement in the overall project scope?
When a new service needs to be mobile enabled, will mobile app developers perform the new app
development and the IA just needs to provide relevant APIs? Please confirm
IA to enable the services across channels as requested by govt, at the same time IA to make publish the APIs for 3rd party service provider to develop the applications
84 Volume 1
11.2 B. Facilitate DC &
DR, (c) Provide backup
tapes/disks for periodic backup of the data, software and other related configurations of MSDG platform in DC and DR
30 What will be the backup policy ? What type of backup is expected for e.g. D2T (Disk to Tape) or D2D2T (Disk to Disk to Tape) ? Do you have any existing backup infra (Tape Library etc.) which can be be used or you want to have separate new setup ?
Existing ESD setup to be used (Disk to Tape System is being used)
85 Volume 1
11.2 B. Facilitate DC &
DR:- d) Provide SAN or similar setup
30 What is the min. capacity required for the SAN storage
?
ESD to provide storage on need basis
Page 31 of 105 86 Volume
1
11.3 Responsible for deployment of the necessary H/W and S/W to operationalize the platform (Ex.
Servers for applications, O/S, Database
Servers, Application Server, Web- Server, Database)
32 Will the h/w and s/w be provided by ESB or IA has to be provide the hardware and s/w
As per RFP, Hardware will be provided by ESD based on Bidders recommendations
87 Volume 1
12.
Estimated Phase wise Services for m- Enableme nt and mobile Transactio ns
1. The following is the indicative transaction volume for ESD services
33 Please confirm the sizing will be done for 3 years projected transaction through Mobile ONLY i.e.
85,50,000 transactions
Indicative transactions are provided, Bidder to propose the solution.
Page 32 of 105 88 Volume
1
12.
Estimated Phase wise Services for m- Enableme nt and mobile Transactio ns
Estimated mobile Transactions per Year
33 Can you please provide the pick concurrency for the mobile apps? Please provide the number of mobile app users along with concurrency?
As per RFP Volume 1, Section 12 (Transaction Volume for ESD & VAS Services)
For Consurrency, Bidder is expected to make necessary assumptions, based on the volumes indicated
89 Volume 1
12.
Estimated Phase wise Services for m- Enableme nt and mobile Transactio ns
2. The following is the indicative transaction volume for VAS services
34 Please let us know the sizing will also include the VAS services?
H/W , S/W size to include all the requirements mentioned in the RFP
90 Volume 1
12 1. The following is the indicative transaction volume for ESD services
34 Can you please provide a high level break-up of channel wise traffic estimate (Like SMS, IVR, App etc.) for the figures given in the table 2 in page no 34?
The bidder is required to make necessary assumptions basis the volumetric info provided by ESD
91 Volume 1
12 3 34 Transaction volume is given in totality – separate
expected number of calls / MOU for IVR And
Count of USSD Sessions / TPS needed
Bidder to make reasonable assumptions
Page 33 of 105 92 Volume
1
Annexure- 1 :
Functional and Technical Feature Complianc e (Product Features)
Transaction Management Support for end- to-end
transaction management system
36 Please let us know if you want to monitor the transaction that will happen at the department applications also?
The monitoring support is required for transaction through MSDG platform.
Deprtment side applications are out of scope
93 Volume 1
Product Feature:
Platform Capabilitie s
Support for high availability of services and platform
38 Query - Are we talking about high availability of all components including DB layer associated with the m- Governance project .Please clarify.
Single point of failure to be avoided and the Bidder need to provide the deployment and application architecture to meet the
requirements stated in the RFP 94 Volume
1
Product Feature:
Security
Support for encryption of data in database
38 Query : Are we also talking about data at rest/storage, network security while data is in transit as well. Please clarify
ESD will provide the data elements which need to be encrypted as and when required - this includes data at rest, data in transit 95 Volume
1
Product Feature : Security
The platform should be able to detect man-in- the middle and repeat attacks wherever possible and desired by business
38 Query - Are we talking about Activity monitoring and blocking on the network, managing SQL
injections/threats , White list, black list, and exception list based enforcement on the network. Please clarify
Bidder is expected to provide the solution to meet the requirement stated which may includes some / all aspects mentioned in the query
Page 34 of 105 96 Volume
1
Product Feature : Security
Ability to log /no- log sensitive information to meet regulatory and Govt of Telangana’s security and privacy guidelines
39 Query - Are we talking about audit trail /audit logs, compliance reporting, SQL analysis, tracking capability of audit data from databases, operating systems, directories etc. Please clarify
The audit trail and log here means all the logs and audit trail required as per Govts. Policy, Regulatory Complaince and Forensic purposes.
97 Volume 1
Section 11.2 – A General managem ent -g
Security Audits 39 Query - Are we talking about audit trail /audit logs, compliance reporting, SQL analysis, tracking capability of audit data from databases, operating systems, directories etc. Please clarify
The audit trail and log here means all the logs and audit trail required as per Govts. Policy, Regulatory Complaince and Forensic purposes.
98 Volume 1
Performan ce / Scalability
Provide documentary evidence of the ability of the database design to scale the DB from 5 TPS to 50 TPS and more as desired by Govt of Telangana from time to time
41 Query: Are we looking for any specific benchmark reports/standards for DB. Please clarify
Citations or benchmark reports or other documentation as desired by ESD
Page 35 of 105 99 Volume
1
Annexure- 1
Annexure-1 : Functional and Technical Feature Compliance (Product
Features) - Frame Work -
Architecture
41 What are the critical applications for which high Availability to be provided in DC & DR ?
All services which have gone live on MSDG should have High availability (for the MSDG functionalities)
100 Volume 1
Annexure- 1
Annexure-1 : Functional and Technical Feature Compliance (Product
Features) - Frame Work -
Architecture
41 Can all the application be virtualized ? Or can we use virtualization technology for the applications?
Bidder to make the reasonable assumptions and suggest feasability
101 Volume 1
Annexure- 1
Annexure-1 : Functional and Technical Feature Compliance (Product
Features) - Frame Work -
Architecture
41 Do you have any existing Active Directory or LDAP infra available which can be used for the new infra or application setup ?or you want to have a separate new infra setup for authentication of users or applications?
Not envisaged at the moment.
Page 36 of 105 102 Volume
1
Annexure- 2 : List of Live ESD Services with Descriptio n
43 Some of the services mentioned can't be enabled through channels like IVR or SMS/USSD due to inherent limitation in the technology (Like filling up application forms for requesting a service can't be done over IVR or SMS/USSD). We assume that it is not mandatory to enable all services across all channels.
Please confirm
The RFP has clearly mentioned the
requirement. It is felt that out of the 600 plus existing services at least 400 services can be delivered through mobile. ESD PMU will decide jointly with the IA on exact numbers.
The idea is that every service will be enabled unless there are strong reasons
103 Volume 1
Annexure- 3: List of ESD Services for Phase- 1 mobile Enableme nt
(Indicative )
94 Total how many phases are there? What is the phase wise time line?
List of services in Annexure-3 about 100 services are expected to Go-Live witin 6 months. ESD to publish the services list (150 each) for subsequent phases (6 months each) the indicative number of services with Go-Live are given in Page 33 & 34
104 Volume 1
Annexure- 5: Training Requireme nts (Indicative )
2. Application Training
99 Does it include mobile app training? (since the mobile app users are the citizens)
Refer to Volume 1, Annexure - 5, for training requirements. The User interface should be self expalnatory with little training.
105 Volume 1
Annexure - 5
100 Kindly clarify , the training space , power , desktops , connectivity,
projector would be provided by department
Training related logistics to be taken care by ESD, but the bidder to make arrangement for the laptop for bidder's team
Page 37 of 105 106 Volume
1
Annexure- 7: Project Launch Document ation Requireme nt
102 Can you please share the project implementation. This is not clear. What is the development/support period, what are the (stage wise) milestones for production and support? Please provide clear implementation plan along with phases, development and
support?Total how many phases are there? What is the phase wise time line?
Indicative implementation plan is provided in Volume 3 page no. 56 & 57. Bidder may provide detailed implementation plan as part of the proposal.List of services in Annexure-3 about 100 services are expected to Go-Live witin 6 months. ESD to publish the services list (150 each) for subsequent phases (6 number of services with Go-Live are given in Page 33 &
34
107 Volume
1 8.13 - - Is it mandate to use freeware for application
and Data base software’s or can use licensed products
Refer to Volume 1, Section 8.13
The Bidder is free to select the technology either open source or propritory along with associated Risks and Benefits. In any case complete cost should be factored into
108 Volume 1
General Does T-Government has any commercial product
stacks from SOA or integration and API management?
Bidder is required to provide MSDG platform and related components
109 Volume 1
General Apart from Service integration ,does it require any workflow or process orchestration cut across different departments of T-Government?
Refer to Volume 1 , Section 6.10
Page 38 of 105 110 Volume
1
General Please provide expected overall User Base and Transaction rate per sec?
Refer to Volume 1, Section 12.
Indicative transactions are provided for ESD &
VAS Services. Accordingly bidder can make necessary assumptions
111 Volume 1
Are the current citizen services being served by 4
different portals?
Refer Volume 1 , Page 7. It's a single portal for Franchisees and 2 portals for online.
112 Volume 1
The current portal architecture consist of API based
integration or point to point integration
ESD to publish APIs for Mobile Services
113 Volume 1
Are the APIs ready for all the services considered for
phase 1?
Not for all. Howver ESD will make the APIs available in time
114 Volume 1
The APIs which will be exposed by existing systems are
SOAP based or restful services?
Based on the requirement bidder to suggest the best possible approach. ESD's decision will prevail.
115 Volume 1
Please share the current architecture, if available. This is the new initiative, please refer to RFP Volume 1 Section 6 & 7 for further details.
116 Volume 1
Please specify the number of payment gateway
integrations required - PGs, Wallets, Netbanking, CCs etc.
The payment instruments to be supported are listed in RFP Volume 1 , Annexure 1- Product Features : Payment (Page 39)
ESD to decide the payment gateway partner(s) 117 Volume
1
What is the expection from real time monitoring. Refer to Volume 1 , Section 6.8.
118 Volume 1
Which mail & message gateway is being used
currently. Are we expected to use the same or propose a new one.
To be provided by ESD. Currently NIC's SMS gateway is used. Bidder may propose alternatives.ESD decision will prevail.
Page 39 of 105 119 Volume
1
Is there any document management system in place
currently. Are we expected to leverage the same.
Not envisaged at the moment. Bidder may suggest if requred as part of the solution with justification
120 Volume 1
Is the bidder expected to create HTML wireframes Refer to Volume 1, Section 11.3 121 Volume
1
How is the user authentication being handled
currently. Are we expected to use the same source of truth for authentication on app and mobile browser.
Bidder to suggest the possible options with justification
122 Volume 1
Please let us know if there is any requirement of user
migration or data migration.
Not envisaged at the moment.
123 Volume 1
Assumption is that we need to maintain all the
transaction history to be shown to the returning user.
Valid assumption
124 Volume 1
Assumption is that MIS reports are required and not
BI driven reports. Please specify an approximate number of reports required for this initiative.
Refer to Volume 1 , Section 6.9
125 Volume 1
Please let us know if there is any preference in terms
of technology stack java, .net etc.
Preference is for open source.Bidder to suggest the technology platform with justifications
126 Volume 1
Please specify the requirement for analytics, if any Refer to Volume 1 , Section 6.9 127 Volume
1
Please specify which all environments are required
(Dev, Test, UAT, Staging, Pre-Prod, Prod etc.)
All environemnst are required. The cost should include all environments. Refer to Volume 1 , Section 9.1 , Point e
Page 40 of 105 128 Volume
1
Please specify the expectations for application testing
(Performance, Security etc.)
Refer to Volume 1, Section 9.8.
Bidder to suggest the approach &
methodology for testing.
129 Volume 1
Is It Okay for the bidder to propose onsite offshore
model.
largely off site except minimum mumber of recources at on site as mentioned in the RFP.
Refer to Volume 1, Section 9.7.
130 Volume 1
Entire RFP
The Complete RFP document section-I does not specific any parameters or metrics to assess the 'Security Capabilities' of the Mobile Service Delivery Gateway. Request Department to Include new specs or Consider the following specs:-
Policy enforcement Enterprise security
Quota mgmt. & rate limiting Content-based routing
Response caching, load-balancing and offload processing
Message format & transport protocol mediation Message format & transport protocol mediation
Bidder to suggest security testing criteria
131 Volume 1
Annexure Annexure-1 : Functional and Technical Feature Compliance (Product Features)
"Platform and service offerings should meet TRAI &
DOT guidelines"
There are no known guidelines that TRAI and DOT publishes for Technology vendors - for Mobile Platforms or API or Gateway providers. Request MeeSeva to kindly clarify what are the specific guidelines or the documents for us to verify and validate
Refer to Volume 1, Section 9.4
Bidder is also required to comply with the regulatory requirements which may be enforced in future
Page 41 of 105 132 Volume
1
Entire RFP
Would all API's be provided by the department for development or IA would be responsible for API Development as well ?
All APIs would be provided by ESD. Refer to Volume 1, Section 7.1
133 Volume 1
Entire RFP
Security is a very important area for MSDG Platform . So if their are Products in the market which can cater the requirement well should they be considered.
Bidder to suggest alternatives with associated risks & justifications
134 Volume 1
General ESD will bear expenses. Who will bear the SMS charges For pull and push
Refer to Volume 1, Section 10.4 135 Volume
1
General Who will bear charges for integrating with payment gateway
Integration to be carried out by the Bidder, PG charges to be paid by ESD
136 Volume 1
General For USSD integration involvement of multiple telecom operators would be there and requirement of a tri-party agreement would be necessary . so kindly clarify department would facilitate the tri-party agreement
As per RFP , agreement will be between ESD and Telco
137 Volume 1
General
Kindly clarify the maximum number of fields that may be present in an application form
It will vary from service to service. Will be decided in due course for each service as and when rolled out
138 Volume 1
General Kindly clarify the maximum number of fields that may be present in an application form. If the filed count is more that 15, it would would challenging for mobile users
Noted
139 Volume 2
2 9 7 Says 360 days from date of agreement. Vol III, Page
36, clause 41.1 says Performance Security should be valid for a period of 3 months after the contract period (which is 36 months + 3).
Please clarify validity period
As per RFP
Page 42 of 105 140 Volume
2
2 In case of BG, EMD shall be valid for 6 months from bid calling date
7 It is recommened that EMD validity be same as bid validity ie 180 days from submission
As per RFP
141 Volume 2
2 360 days from
the date of agreement
7 What should be the duration of the PBG ? Refer Volume 3, Clause 41
Should be valid upto a period of 3 months after the contract ( Renew after 360 days) 142 Volume
2
6 - 10 Diagram does not mention AppStore onboarding
requirements.
Other sections mention the same. We are assuming:
- AppStore is a requirement
- Citizen Service Apps will be tested, certified by 3rd party and onboarded by ESD
- Private Apps can also be onboarded subject to meeting ESD norms and revenue share agreed to - Private apps will be tested & on-boarded at a minimum fees as ESD should not take the costs - Once private apps are on-boarded, how will citizen know about the new app?
- How will private app provider compensated – manual/automation through SDP Please confirm?
Refer volume 1, Section 9.8 ,Section 10.3 &
other related sections.
Page 43 of 105 143 Volume
2
4.6 In exceptional circumstances, the TSTS/ESD may solicit the bidders' consent to an extension of the period of validity. The request and the responses thereto shall be made in writing.
The bid security shall also be suitably extended.
However a bidder granting the request will not be permitted to modify its bid.
14 It is recommended that in case of extension of bid is required , TCS be allowed to modify the bis
As per RFP
Page 44 of 105 144 Volume
2
4.12. Bid security i.e., Earnest Money Deposit (EMD)
4. Unsuccessful bidder's bid security (EMD) will be
discharged or returned as promptly as possible as but not later than thirty (30) days after the
expiration of the period of bid validity prescribed by TSTS.
15 Request to modify the clause as below:
4. Unsuccessful bidder's bid security (EMD) will be discharged or returned as promptly as possible as but not later than thirty (30) days after the expiration of the period of bid validity prescribed by TSTS or notification of award to the successful bidder, whichever is earlier.
As per RFP
Page 45 of 105 145 Volume
2
4.12. Bid security i.e., Earnest Money Deposit (EMD)
6. The bid security may be forfeited:
a. if a bidder withdraws its bid during the period of bid validity or b. in the case of a successful bidder, if the bidder fails:
1. to sign the contract in time;
or
2. to furnish performance security in time.
16 Request to modify the clause as below:
6. The bid security may be forfeited:
a. if a bidder withdraws its bid during the period of bid validity or
b. in the case of a successful bidder, if the bidder, even after the deviations submitted by the bidder are considered adequately, fails:
1. to sign the contract in time; or
2. to furnish performance security in time.
As per RFP
146 Volume 2
5.5 Evaluation of Pre- qualificatio n bids
Pre-qualification criteria table SI No 5.
b. This platform should have handled live transactions in at least 3 of the following 5 channels as defined below:
19 We assume that the references of all the channels need not necessarily be from the same project. Can you please confirm this?
Customer citations required - can be from different projects as long as it meet the minimum volume
Page 46 of 105 147 Volume
2
5 5.5
S.No.5.a
19 Request to consider:
The Bidder should have experience in platform/
Mobile Applications which are Commercially deployed in at least 2 entities - (i.e. in Telecom Operators or Banks or Central /State Governments/PSUs) in India or in equivalent authorities in Countries outside India).
As per RFP
148 Volume 2
5 5.5.5.a 19 We have used the Platform to develop our B2C Apps which have more than 1 Lac downloads and more than 10 Lac transactions monthly. Please allow to geve self attested certificates with Play store and Analytics snap shots
As per RFP
149 Volume 2
5 5.5.5.a 19 One of the project that we are working on National level is under deployment. Please allow to share Work Order along with Self Certification
Commercially deployed platform means platform which is live.
150 Volume 2
5 5.5.5.c 19 We have developed B2C App for which we have more
than 1 Lac downaloads and huge transactions by customers have all these payment modules
connected. Please allow this App in eligibility with self certification
As per RFP. Downloading is not verifiable
Page 47 of 105 151 Volume
2
5.5.
Evaluation of Pre- qualificatio n bids
The platform proposed by the bidder or prime bidder in response to this
RFP 5. Relevant Past
Experiences a) Platform must have been Commercially deployed in at least 3 entities - (i.e. in either Telecom Operators or Banks or Central /State
Governments/PS Us ) in India or in equivalent authorities in Countries outside India).
b) This platform should have handled live transactions in at least 3 of the following 5 channels as defined below:
19 Request you to change as below.
The platform proposed by the bidder or prime bidder in response to this RFP Since these are new digital initiatives, the qualification criteria should be satisfied either by SI or by the OEM.
The criteria is self-explanatory - we are referring to the platform proposed by the bidder / prime bidder and is either by the SI or the OEM
Page 48 of 105 152 Volume
2
5.5 5.5- Pt 5 19 Please include SSDG related past experience also and make it optional with MSDG past experience
requirement so that the bidders having successful experience in SSDG alone can also participate
As per RFP
153 Volume 2
5 5.5 19 Request you to modify as The Bidder or Prime Bidder should have a minimum annual turnover of Rs. 500 Crores per year during the last 3 financial years (FY 2013-14, FY 2014-15, FY 2015- 16) from Information Technology related services
As per RFP as more bidders are desired.
154 Volume 2
5 5.5 19 Kindly modify as The bidder should have a positive networth of Rs.300 crores for last 3 consecutive years (FY2012-13, 2013-14 and 2014-15) OR (FY2013- 14,2014-15 and 2015-16).
As per RFP asmore bidders are desired
Page 49 of 105 155 Volume
2
5.5.Sl.No.3 The Bidder or Prime Bidder should have a minimum annual turnover of Rs.
30 Crores per year during the last 3 financial years (FY 2013- 14, FY 2014-15, FY 2015- 16) from Information Technology related services
19
We are request you to please amend the clause as “The Bidder or Prime Bidder should have a minimum average annual turnover of Rs. 25 Crores during the last 3 financial years (FY 2013-14, FY 2014-15, FY 2015- 16) from Information Technology related services
Please refer to Corrigendum / Addendum
156 Volume 2
5.5.Sl.No.5 - Relevant Past Experience
The platform proposed by the bidder or Prime bidder (In case of Consortium) in response to this RFP:
19
We request you to please amend this clause as
“The platform proposed by the bidder or Prime bidder / Consortium Partner (In case of Consortium) in response to this RFP:”
Please refer to Corrigendum / Addendum
Page 50 of 105 157 Volume
2
2) In case of consortium, the consortium partner individually to have 10 Cr per year as minimum turnover during the last 3 financial years (FY 2013 -14, FY 2014-15, FY 2015-16) from Information Technology related services
19 Request to change to “The prime bidder should have positive net worth & cumulative turnover of Rs. 25Crs.
from last 3 financial years i.e. (FY 2013 -14, FY 2014- 15, FY 2015-16) from Information Technology related services
As per RFP
Page 51 of 105 158 Volume
2
The Bid can be
submitted by an individual organization or a consortium of companies having maximum 2 members. In case of a consortium, the same shall be formed under a duly stamped consortium agreement and signed by the authorized signatories of the companies.
In the event of a consortium, one of the partners shall be
designated as a
“Prime Bidder”.
Prime Bidder shall be solely responsible for the successful completion of the entire project.
19 Request to allow upto 3 consortium partners namely 1. Platform vendor, 2. Telecom partner 3.
Implementation partner
As per RFP since Telecom infrastructure is by ESD
Page 52 of 105 159 Volume
2
5.5 2 19 Maximum 2 members means 1 Prime bidder
and 2 Consortium Partners or not? If not please allow 2 Consortium Partners
As per RFP
160 Volume
2 5.5 3 19 Allow consortium partner minimum turnover
2Cr per anum for last 3 years or 6 Cr for last 3 Years.
As per RFP
161 Volume 2
5.5 5.a 19 Documets can be submitted as copies of work orders in case of ongoing projects and - Copies of work order along with completion certificates can be submitted for completed projects
Commercially deployed platform means platform which is live.
162 Volume 2
5.5 5.B 19 We request you to change the clause to "This platform should have handled live
transactions in at least 1 of the following 5 channels as defined
As per RFP - since the platform should be proven one.
Page 53 of 105 163 Volume
2
5.5.
Evaluation of Pre- qualificatio n bids
5. Relevant Past Experiences IVR: Minimum 100,000 voice calls(inbound or outbound) in a month
SMS: Minimum 1 million SMS in a month
USSD: Minimum 100,000 USSD requests in a month Mobile Web:
Minimum 2 mobile web applications (2 citations from the customer required along with the details of the mobile web application and URL) Smart Client:
Minimum 2 Smart Client applications across multiple mobile operating systems one of which must be Android (2 citations from the customer
20 The qualification criteria should be satisfied either by SI or by the OEM. Since the initiative is new, digital and the acceptance of the web / mobile methods were not so popular earlier, request you to reduce the volumetrics.
Qualification criteria can be either by the SI or the OEM
Page 54 of 105 164 Volume
2
5.5.
Evaluation of Pre- qualificatio n bids
5. Relevant Past Experiences c) The Proposed platform must have handled mobile payments through one of the modes defined below:
1. Payment gateway integration to process Card based (Credit / Debit Card) payments 2. Account based (UPI/IMPS or Direct Account Connectivity) payments 3. Wallet based payments d) The
installations cited to address the requirements specified under sections 5b, 5c must have gone live in the last 5 years (calculated backwards from the date of publishing of tender)
20 The qualification criteria should be satisfied either by SI or by the OEM.
Qualification crateria can be either by the SI or the OEM
Page 55 of 105 165 Volume
2
5.5 SL. No 5 20 what is outbound in IVR mean? do you need Voice blast?
Understanding is correct 166 Volume
2
5 5.5 20 Kindly remove this clause As per RFP
167 Volume
2 5.5 5.C 20 We request you to change the cluse to "The bidder should have expertise in payment gateway integration"
As per RFP
168 Volume 2
5.6 (d) Preference to domestically manufactured goods
21 Will any price preference be given to domestic products or will equal weight age given for two equally priced similar products?
As per RFP
169 Volume 2
III. Prior Experience
24 The qualification criteria should be satisfied either by SI or by the OEM.
Qualification crateria can be either by the SI or the OEM
170 Volume 2
5.17 The FAT may be carried out by ESD (MEE SEVA) or 3rd party selected by ESD (MEE SEVA). The FAT will be completed within 3 months of starting the FAT activity.
29 Request clarification as vol 3 of the RFP suggests FAT to be completed in 4 months and the entire
implementation timeline is 12 weeks which is 3 months. Please provide clarity on the timelines.
As per RFP. Efforts will be made to complete FAT as quickly as possible.